A new offshore call center project is vital for a company's branch offices. The project is at
the end of the planning phase when the project manager is informed by the sponsor that
the project will be delayed due to reprioritization.
What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a video conference to inform the branch office stakeholders about the project
delay.
Question 532Choose 1
Due to an anticipated expansion, a company procured new technology. The project team
responsible for using this technology does not have experience with it.
What should the project manager do?
Show answerHide answer
Correct answer: CPropose training for the project team in batches on the new technology.
Question 533Choose 1
A project lead is managing an agile project. The project activities, which have been placed
in a backlog, still need to be refined and prioritized.
What should the project lead use for backlog refinement considering the sprints are 2
weeks long?
Show answerHide answer
Correct answer: CSixty minutes every sprint going through stories that are higher priority.
Question 534Choose 1
A software development project is about to start. The product owner and project manager
cannot agree on which programming language to use from the available two. The company
lacks experienced developers in the product owner's preferred language; however, they
are very skilled in the other language.
What should the project manager do?
Show answerHide answer
Correct answer: APersuade the product owner to use the language preferred by the developers.
Question 535Choose 1
Customers are concerned about the quality of an interim software system for a project. The
quality control team has approved the software, but the customers are complaining that
some functions do not comply with the requirements.
What should the project manager do to prevent this from happening again?
Show answerHide answer
Correct answer: DRevise the product acceptance specifications.
Question 536Choose 1
A project manager is working on an ongoing construction project. The designer notifies the
project manager about materials that were not included in the budget due to a technical
mistake.
What should the project manager have done to avoid this situation?
Show answerHide answer
Correct answer: DUsed past projects as a reference during budget estimations
Question 537Choose 1
A project manager is leading the construction of a branch office building for a national
bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
Show answerHide answer
Correct answer: CEvaluate contract and administrative tasks.
Question 538Choose 1
A project manager's team has been working very hard to meet a critical deadline. Some
project team members are experiencing burnout due to the high workload.
What should the project manager do first to manage the team's workload effectively?
Show answerHide answer
Correct answer: BEncourage open communication and involve the team in task distribution decisions.
Question 539Choose 1
Multidisciplinary teams will be needed for a project. The project manager asks the project
planner to create a consolidated schedule. The project manager determines from the
consolidated schedule that the project's finish date exceeds the requested finish date.
What should the project manager suggest to the planner to analyze this issue?
Show answerHide answer
Correct answer: BVerify the critical path of the consolidated project schedule.
Question 540Choose 1
During a sprint, the team is experiencing conflict because the customer asks for additional
features that increase the complexity. The scrum master is trying to resolve the conflict.
Which approach should the scrum master use?
Show answerHide answer
Correct answer: BApproach the product owner to determine the next course of action and update the
backlog.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.