Question 531 Choose 1
A new offshore call center project is vital for a company's branch offices. The project is at the end of the planning phase when the project manager is informed by the sponsor that the project will be delayed due to reprioritization.

What should the project manager do?
Show answerHide answer

Correct answer: B Schedule a video conference to inform the branch office stakeholders about the project delay.

Question 532 Choose 1
Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?
Show answerHide answer

Correct answer: C Propose training for the project team in batches on the new technology.

Question 533 Choose 1
A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.

What should the project lead use for backlog refinement considering the sprints are 2 weeks long?
Show answerHide answer

Correct answer: C Sixty minutes every sprint going through stories that are higher priority.

Question 534 Choose 1
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language.

What should the project manager do?
Show answerHide answer

Correct answer: A Persuade the product owner to use the language preferred by the developers.

Question 535 Choose 1
Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.

What should the project manager do to prevent this from happening again?
Show answerHide answer

Correct answer: D Revise the product acceptance specifications.

Question 536 Choose 1
A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: D Used past projects as a reference during budget estimations

Question 537 Choose 1
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?
Show answerHide answer

Correct answer: C Evaluate contract and administrative tasks.

Question 538 Choose 1
A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team's workload effectively?
Show answerHide answer

Correct answer: B Encourage open communication and involve the team in task distribution decisions.

Question 539 Choose 1
Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?
Show answerHide answer

Correct answer: B Verify the critical path of the consolidated project schedule.

Question 540 Choose 1
During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?
Show answerHide answer

Correct answer: B Approach the product owner to determine the next course of action and update the backlog.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt