During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.
The customer is asking the project manager for guidance.
What should the project manager do?
Show answerHide answer
Correct answer: DIn the planning meeting, focus on releasing a minimum viable product (MVP) quickly and
getting feedback from the end users.
Question 2Choose 1
During an iteration demo, a customer noticed an enhancement they would like to make to
the product. What should the team do next?
Show answerHide answer
Correct answer: DAsk the product owner to prioritize the item with the customer
Question 3Choose 1
During project execution, a key team member has to be moved to another critical project
for the company. Currently, there is no other team member who can fill that role.
What should the project manager do first?
Show answerHide answer
Correct answer: DEvaluate the impact of the key team member's removal from the project, look for
alternatives, and submit a change request if required.
Question 4Choose 1
A specialized team member has just received news that they must leave the office for
several weeks They have approximately two workdays until they will leave and then they
will become unavailable through any communication channels. There is a key deadline
approaching
What should the agile project manager do?
Show answerHide answer
Correct answer: BAsk the team member to work with their peers to knowledge share
Question 5Choose 1
During the initiation stage of a multimedia exhibition-design project the project manager is
developing the project management plan What should the project manager do to complete
this task?
Show answerHide answer
Correct answer: CClarify the high-level business requirements with the event organizer as a basis for
forming the deliverables list.
Question 6Choose 1
Two key team members suggest different options to prevent time overruns and delays.
There is a conflict between these two team members because of their divergent views.
What should the project manager do next?
Show answerHide answer
Correct answer: ASchedule a meeting between the team members to find a solution.
Question 7Choose 1
A project manager brings in a new team member from an agile environment to work in a
predictive environment The project manager expects to leverage the new team member's
agile experience with the existing team members.
What should the project manager do to integrate the new team member effectively?
Show answerHide answer
Correct answer: CSet expectations with the new team member and explain what is needed
Question 8Choose 1
A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
Show answerHide answer
Correct answer: BInclude knowledge transfer sessions between the project and operations teams at every
stage.
Question 9Choose 1
During a project status update by the project management office (PMO), the CEO is
concerned that the status of all projects suddenly changed from green to red, without
warning. Upper management is used to reading traditional reports related to progress and
cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?
Show answerHide answer
Correct answer: BExplore reporting the earned value (EV) key performance indicators (KPls) using agile
progress as an input.
Question 10Choose 1
The project manager of a hybrid project learns that a stakeholder has approached a team
member directly to request a change This change will impact the project m a significant
way The project manager should ten the stakeholder that the correct procedure tor new
requirements is to provide a request directly to whom?
Show answerHide answer
Correct answer: AProduct owner
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.