Question 631 Choose 1
After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?
Show answerHide answer

Correct answer: B Assist the team in proposing a minimum viable product (MVP)

Question 632 Choose 1
A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?
Show answerHide answer

Correct answer: C Facilitate a discussion and come to an agreement about what quality means for both the team and the stakeholders.

Question 633 Choose 1
During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?
Show answerHide answer

Correct answer: A Timebox the team members’ debate to ensure the activity is completed on time.

Question 634 Choose 1
A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive equipment. The project manager is aware that some purchase amounts require higher levels of approval. What should the project manager do to properly manage the purchase of equipment?
Show answerHide answer

Correct answer: A Agree on a purchasing approval escalation method according to organizational governance

Question 635 Choose 1
During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?
Show answerHide answer

Correct answer: A Use a network diagram to show that the delayed tasks are not on the critical path.

Question 636 Choose 1
There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?
Show answerHide answer

Correct answer: C Review and update the communications management plan

That's the last free question

You've seen the free 30% (636 of 2,130 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt