The team's work assignments have been generically distributed. A new team member is
performing slower than expected.
What should the project manager do?
Show answerHide answer
Correct answer: DAssess the new team member's skills in order to determine additional training needs.
Question 542Choose 1
A project team is not motivated and is producing the bare minimum. The team has no
interest in keeping pace with the aggressive project schedule.
Show answerHide answer
Correct answer: ASeek to understand the sentiments of each team member and then work with them to
address their concerns.
Question 543Choose 1
A project is on schedule. However, during a site visit, a project manager notices that the
contractor's productivity is low.
What should the project manager do?
Show answerHide answer
Correct answer: BDiscuss the need to increase productivity with the contractor.
Question 544Choose 3
The project manager is planning a project with several legal aspects for the city's
municipality. The project is expected to take a year and will require a lot of paperwork since
it involves multiple stakeholders, including the city's court.
What three actions should the project manager do? (Choose 3)
Show answerHide answer
Correct answer: A, D, ELeverage the project governance system to track and manage the project artifacts.Ensure the project artifacts are kept up to date and accessible to all stakeholders.Work with the team to determine the process to manage the project artifacts.
Question 545Choose 1
Following an investment decision-making meeting for a project, a change to the
organizational structure takes place in a multinational company. Due to the organizational
change, internal stakeholders are referring the project manager to various other personnel
for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
Show answerHide answer
Correct answer: DObtain the latest organizational chart and send an email to the appropriate person
requesting budget approval.
Question 546Choose 1
During a daily meeting of a challenging project, two team members started to argue on the
preferred solution based on their assumptions. The situation prevented the progress to the
next phase of development, which could impact the finish date of the project.
What should the project manager do next?
Show answerHide answer
Correct answer: DMeet with the team members to discuss the priority of the project schedule.
Question 547Choose 1
A project lead has asked a project team to update a 200-page project report and send it to
the project sponsor. The team mentioned that nobody reads the report and it takes time
away from higher priority work. The project lead responded that they have to show all the
work that they performed in every iteration.
What should the project lead do first?
Show answerHide answer
Correct answer: BEnsure the communications methods, channels, frequency, and level of detail for the
stakeholders are what is needed.
Question 548Choose 1
A project team consisting of 13 people was set up three months ago. As part of the
transition to agile, a scrum master was assigned to the project. The scrum master wants to
know the status of the team's development stage. The project manager believes that the
team has passed the "storming" stage.
Which indicators should be used to determine the team's development stage?
Show answerHide answer
Correct answer: BTeam members share information and experiences.
Question 549Choose 1
After establishing a cost baseline and the appropriate cost management plan for a complex
hybrid project, the project is still being challenged with cases of budgetary variations. What
should the project manager do?
Show answerHide answer
Correct answer: ATrack budget variations and work with the key stakeholders to adjust as necessary.
Question 550Choose 1
A project manager is in the middle of executing the construction of a high-rise plaza when
the government regulatory agency announces an increase in the price of fuel. The project
still has seven months left on the schedule.
What should the project manager do first?
Show answerHide answer
Correct answer: AMeet with the vendors to evaluate the impact on the budget.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.