Question 541 Choose 1
The team's work assignments have been generically distributed. A new team member is performing slower than expected.

What should the project manager do?
Show answerHide answer

Correct answer: D Assess the new team member's skills in order to determine additional training needs.

Question 542 Choose 1
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
Show answerHide answer

Correct answer: A Seek to understand the sentiments of each team member and then work with them to address their concerns.

Question 543 Choose 1
A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?
Show answerHide answer

Correct answer: B Discuss the need to increase productivity with the contractor.

Question 544 Choose 3
The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)
Show answerHide answer

Correct answer: A, D, E Leverage the project governance system to track and manage the project artifacts.Ensure the project artifacts are kept up to date and accessible to all stakeholders.Work with the team to determine the process to manage the project artifacts.

Question 545 Choose 1
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?
Show answerHide answer

Correct answer: D Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

Question 546 Choose 1
During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?
Show answerHide answer

Correct answer: D Meet with the team members to discuss the priority of the project schedule.

Question 547 Choose 1
A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.

What should the project lead do first?
Show answerHide answer

Correct answer: B Ensure the communications methods, channels, frequency, and level of detail for the stakeholders are what is needed.

Question 548 Choose 1
A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team's development stage. The project manager believes that the team has passed the "storming" stage.

Which indicators should be used to determine the team's development stage?
Show answerHide answer

Correct answer: B Team members share information and experiences.

Question 549 Choose 1
After establishing a cost baseline and the appropriate cost management plan for a complex hybrid project, the project is still being challenged with cases of budgetary variations. What should the project manager do?
Show answerHide answer

Correct answer: A Track budget variations and work with the key stakeholders to adjust as necessary.

Question 550 Choose 1
A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?
Show answerHide answer

Correct answer: A Meet with the vendors to evaluate the impact on the budget.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt