Question 551 Choose 1
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
Show answerHide answer

Correct answer: A Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

Question 552 Choose 1
A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?
Show answerHide answer

Correct answer: D Schedule team-building activities as required.

Question 553 Choose 1
A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.

What should the project manager do?
Show answerHide answer

Correct answer: B Approve the team member's request as it will increase motivation.

Question 554 Choose 1
A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?
Show answerHide answer

Correct answer: B Investigate the client's project reports and proceed to negotiate the levying of any penalties.

Question 555 Choose 1
A project manager has just been designated to lead an approved project with a virtual team. The team members are from several countries and have never met before.

In order to promote team engagement and introduce the project team, what should the project manager do?
Show answerHide answer

Correct answer: D Schedule a kickoff meeting to present the whole project team.

Question 556 Choose 1
A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?
Show answerHide answer

Correct answer: C Intensification

Question 557 Choose 1
A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?
Show answerHide answer

Correct answer: B Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

Question 558 Choose 1
A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?
Show answerHide answer

Correct answer: C Arrange a required training session for the team member.

Question 559 Choose 1
During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?
Show answerHide answer

Correct answer: C Record the situation in the issue log immediately and evaluate the impact of losing the resource.

Question 560 Choose 1
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
Show answerHide answer

Correct answer: D Establish a common language of terms with which to communicate with the provider.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt