Question 1 Choose 1
A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?
Show answerHide answer

Correct answer: C Reviewed benefits realization with the customer regularly and constantly aligned expectations

Question 2 Choose 1
After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?
Show answerHide answer

Correct answer: B Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

Question 3 Choose 1
A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?
Show answerHide answer

Correct answer: A Schedule a conference call with the project team.

Question 4 Choose 2
A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)
Show answerHide answer

Correct answer: A, C Review the list of stakeholders that will be affected by starting this business initiative.Describe the outcome of the project and business value to all company stakeholders.

Question 5 Choose 1
A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?
Show answerHide answer

Correct answer: D Discuss the situation with the project team member

Question 6 Choose 1
A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?
Show answerHide answer

Correct answer: B Mentor the team and stakeholders to ensure domain knowledge is exchanged during sprints

Question 7 Choose 1
It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?
Show answerHide answer

Correct answer: C Put more emphasis on the definition of done (DoD)

Question 8 Choose 1
A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?
Show answerHide answer

Correct answer: D Ensured the new team member had access to the quality management plan

Question 9 Choose 1
During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?
Show answerHide answer

Correct answer: C Ensure the definition of done (DoD) is understood by all team members.

Question 10 Choose 1
One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?
Show answerHide answer

Correct answer: D Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt