A project is behind schedule because of a delayed equipment installation. This is affecting
many other activities. The manager responsible for the
equipment delivery notified the project manager that there is a capacity issue for the team
doing the installation.
What should the project manager have done to prevent this situation from happening?
Show answerHide answer
Correct answer: CConducted periodic reviews with the manager on resource availability.
Question 502Choose 1
Anew law was published about zoning permits for telecom towers. This may cause cost
and schedule overruns for the new network rollout.
What should the project manager do?
Show answerHide answer
Correct answer: AAssess and prioritize the impact of the new law on the project plan.
Question 503Choose 1
During a regular project progress meeting, the CEO informed the project manager that a
major stakeholder has been unaware of recent developments on the project. The
project manager is sure that the stakeholder was duly identified and classified in the
stakeholder register.
Which project document should the project manager review in order to determine the
reason for this issue?
A company is implementing a project with team members located in different countries and
time zones. Individual performance is satisfactory, but the team's performance as
a whole is low, especially in terms of group activities.
What should the project manager do?
Show answerHide answer
Correct answer: DFacilitate communication and team building.
Question 505Choose 3
A company hired a new project lead to incorporate some agile practices.
Which three changes should the project lead incorporate in the existing team meetings?
(Choose 3)
Show answerHide answer
Correct answer: A, B, EAdd sprints and sprint reviews as necessary.Agree with the team on some ground rules.Encourage everyone to participate in the daily meetings.
Question 506Choose 1
A project team member is sick and will not be able to return to the project for a few weeks.
During the daily meeting, the team shares their concerns as the sick team member was the
only one skilled in the component they were developing.
What should the project manager have done to prevent this?
Show answerHide answer
Correct answer: DFacilitated cross-functional knowledge transfer during the project.
Question 507Choose 1
A project manager is working on a software development project for an oil and gas client
using an agile approach. The project manager is having difficulty preparing the schedule
because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?v
Show answerHide answer
Correct answer: AIterative scheduling
Question 508Choose 1
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased
equipment will be delayed. The project manager is concerned that this will directly effect
the project schedule.
What should the project manager do next?
Show answerHide answer
Correct answer: BUpdate the risk register and discuss it with the project stakeholders.
Question 509Choose 1
An agile team has been assigned to a project that mandates the implementation of
changes to key government products. The team has been given 6 months to fulfill this
mandate.
What should the team lead do next?
Show answerHide answer
Correct answer: BCreate the epics at a high level for the requirements and begin grooming sessions.
Question 510Choose 1
The scope of a project is to replace the street signs within a 10-km radius. The client does
not want to sign the project closure report if the radius
is not extended by 1 km, to be aligned with the council's development plan.
What should the project manager do?
Show answerHide answer
Correct answer: DObtain formal acceptance for the completed work and submit a change request.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.