In the daily check-in meeting, a team member informs the project team that the licenses for
one of the components that will be used will expire in
a couple of months. The licensing cost is significant.
What should the project manager do next?
Show answerHide answer
Correct answer: AEvaluate the impact of nonrenewal of the license.
Question 2Choose 1
A project manager is tasked with developing a coaching model to support and recognize
team members' growth.
What should the project manager consider when defining their coaching strategy?
Show answerHide answer
Correct answer: CIndividual and personal objectives
Question 3Choose 1
A project manager was replaced in the early phases of a new project. The new project
manager discovers that the business team is not supporting the project. After
discussing these concerns with the team, it is determined that the project does not have the
full support of senior management.
What should the new project manager do next?
Show answerHide answer
Correct answer: CStudy the stakeholder analysis to understand which stakeholder holds the most
influence and seek their assistance.
Question 4Choose 1
A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The
project manager is working on a predictive project and thinks this request will distract the
team and delay the project.
What should the project manager do first?
Show answerHide answer
Correct answer: AAssess and analyze the impact of using these metrics.
Question 5Choose 1
A project team member, who is inexperienced in system development work is not
performing well. Currently, there are no other staff members
available who are qualified to complete the work.
What should the project manager do?
Show answerHide answer
Correct answer: AAssess the team member's development requirements and arrange for the team
member to receive training.
Question 6Choose 1
A project stakeholder complained that they did not receive an important delivery that was
stated in the schedule. The team member responsible for this deliverable explained that
they sent an email to the stakeholder, advising them that the deliverable would not be
delivered on time.
What should the project manager have done to avoid this situation?
Show answerHide answer
Correct answer: DCommunicated with the stakeholder directly regarding the delivery delay.
Question 7Choose 1
A healthcare company is in the process of deploying an innovative healthcare solution
globally. The project team has completed a limited release.
The stakeholders have raised concerns about global healthcare guidelines and risks.
What should the project manager do next?
Show answerHide answer
Correct answer: CReview compliance and regulatory requirements with stakeholders.
Question 8Choose 1
After conducting a performance assessment, the project manager identified that some gaps
still exist. What should the project manager ensure?
Show answerHide answer
Correct answer: BPerformance improvement programs are organized for all team members who were
assessed.
Question 9Choose 1
A project manager is managing an agile project for the first time. Early on, the project
manager discovers the team is struggling to agree on the scope of a feature during a sprint.
How should the project manager help the team resolve the issue?
Show answerHide answer
Correct answer: DEncourage the team to collaborate to resolve their understanding of the feature.
Question 10Choose 1
A project manager is leading a strategic and competitive advantage project for a healthcare
organization that is in its testing phase. The team has
been working on this project for 6 months, and the morale of the team is low due to the
schedule.
What can the project manager do to motivate the team?
Show answerHide answer
Correct answer: CSpeak with the project management office (PMO) and request a 2-week extension of the
schedule so the team can have rotational time off.
Full mock exam