A project manager notices that a team member is upset during a team meeting. The project
manager assesses the situation and determines that the team member does not
collaborate with some of the other team members.
What should the project manager do?
Show answerHide answer
Correct answer: CReach out to the team member to discuss and address their concerns as soon as
possible.
Question 562Choose 1
An experienced project manager has been assigned to a hybrid project that requires an
extensive amount of information to be updated. Which tool should the project manager use
along with the team?
Show answerHide answer
Correct answer: BKanban board
Question 563Choose 1
To limit the amount of time and cost of using a contract programming firm, a product
manager announces that the developers will not be paid for unrequested embellishments to
the product. What should the development team and scrum master do to ensure they are
paid for all their work?
Show answerHide answer
Correct answer: CEnsure that the task board is used as an information radiator and all stories have
enough detail to build the required feature or function.
Question 564Choose 1
Due to scope changes, some of the risks identified during the initiation phase have
materialized into issues. What should the project manager do next?
Show answerHide answer
Correct answer: ASubmit a request to access contingency reserves and accept the changes.
Question 565Choose 2
An IT team has reached out to the project manager for guidance on which communication
method to use when system downtime will impact the resources working on the project.
Which two communication methods should the project manager recommend? (Choose 2)
Show answerHide answer
Correct answer: A, ECommunicate via email to the project's email distribution group.Communicate verbally to the key project stakeholders.
Question 566Choose 1
A project manager with agile experience is part of an organization that is transitioning to
agile. The project manager was assigned to the first agile project by the project
management office (PMO). The PMO manager asked the project manager if an existing
governance from a previous project would be suitable to use in the current agile project.
How should the project manager respond?
Show answerHide answer
Correct answer: CAn agile approach is easily adaptable.
Question 567Choose 1
A project manager is planning a project to build a research center with the installation of
scientific equipment. Since the research topic is new and unfamiliar, the equipment
required might change during project execution.
How should the project manager plan this project?
Show answerHide answer
Correct answer: AUse a different project life cycle approach for the different parts of this project by
adopting a hybrid approach.
Question 568Choose 1
A high-tech borehole project was initiated with the goal of providing water for a rural
community of 1500 villagers located in an arid region. The project was completed with a
cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six
months after its completion, it is determined that the villagers could not access water.
What caused this situation to occur?
Show answerHide answer
Correct answer: BThe requirements gathering was inadequate.
Question 569Choose 3
A project team is experiencing communication issues during project execution. The project
manager realizes that the communications management plan needs to be reviewed.
Which are three fundamental actions the project manager should take? (Choose 3)
Show answerHide answer
Correct answer: A, C, DDecide on the frequency of communications.Determine the appropriate methods of communication.Identify the level of detail needed by different stakeholders.
Question 570Choose 1
A project to support an organizational transformation is in the planning phase.
Transformation is the project sponsor's idea and is not aligned with key stakeholders
because they all have different opinions about the project outcomes.
What should the project manager do next?
Show answerHide answer
Correct answer: DConduct a workshop on project goals and deliverables with the key stakeholders.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.