Question 561 Choose 1
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?
Show answerHide answer

Correct answer: C Reach out to the team member to discuss and address their concerns as soon as possible.

Question 562 Choose 1
An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?
Show answerHide answer

Correct answer: B Kanban board

Question 563 Choose 1
To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?
Show answerHide answer

Correct answer: C Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.

Question 564 Choose 1
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
Show answerHide answer

Correct answer: A Submit a request to access contingency reserves and accept the changes.

Question 565 Choose 2
An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)
Show answerHide answer

Correct answer: A, E Communicate via email to the project's email distribution group.Communicate verbally to the key project stakeholders.

Question 566 Choose 1
A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?
Show answerHide answer

Correct answer: C An agile approach is easily adaptable.

Question 567 Choose 1
A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?
Show answerHide answer

Correct answer: A Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

Question 568 Choose 1
A high-tech borehole project was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six months after its completion, it is determined that the villagers could not access water.

What caused this situation to occur?
Show answerHide answer

Correct answer: B The requirements gathering was inadequate.

Question 569 Choose 3
A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.

Which are three fundamental actions the project manager should take? (Choose 3)
Show answerHide answer

Correct answer: A, C, D Decide on the frequency of communications.Determine the appropriate methods of communication.Identify the level of detail needed by different stakeholders.

Question 570 Choose 1
A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.

What should the project manager do next?
Show answerHide answer

Correct answer: D Conduct a workshop on project goals and deliverables with the key stakeholders.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt