A key project stakeholder who was a big supporter and motivator for the project team is
leaving the organization The project team is experiencing low morale and poor teamwork
What should the project manager do to improve morale?
Show answerHide answer
Correct answer: BBuild team connections and emotional bonds
Question 2
During a project's planning session, the project team discussed selecting the required
information to be included in the monthly progress report This report will be produced in the
Executing and Monitor and Controlling phases and will be used when communicating
project progress to the client
Match the scenario on the left with the action on the right.
Show answerHide answer
Explanation
Question 3Choose 1
A project manager is leading an in-house company project in its very early stages This
current project is similar to another project that ended a year ago
What should the project manager do to analyze the involved stakeholders?
Show answerHide answer
Correct answer: BUse lessons learned from the previous project as a guide for the current project's
stakeholder register
Question 4Choose 1
One of a project manager’s team members is continuously improving This team member
has been a role model and mentor to others in the organization
How should the project manager acknowledge this team member’s commitment?
Show answerHide answer
Correct answer: BAppreciate this team member’s performance throughout the project life cycle
Question 5Choose 1
A new team member has joined an agile project, replacing a team member who recently
left The project team needs the new team member to speed up their ability to contribute
effectively to the project
What should the project manager do to help in this situation?
Show answerHide answer
Correct answer: BSchedule knowledge transfer sessions and assign less complex tasks to the new team
member
Question 6Choose 3
A company is changing their current business model The change requires implementing a
complex project using multiple agile teams.
What three options should the project manager have the testing team adopt as testing
mechanisms? (Choose three)
Show answerHide answer
Correct answer: B, D, ESecurity and performance testingStory testingTests based on behavior and test-driven development
Question 7Choose 1
During the third iteration, the team encounters a major delay that has not had significant
improvements over the last few weeks What should the project manager do?
Show answerHide answer
Correct answer: ARetrospect frequently and suggest improvements.
Question 8Choose 1
A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product
owner is confused as to how to start delivering the functionalities required
How should the project manager assist the product owner?
Show answerHide answer
Correct answer: ACoach the product owner on how to create a product backlog
Question 9Choose 2
The project manager has observed that two team members have been arguing with each
other openly at meetings To push their ideas through, each team member individually
spoke with the sponsor directly and made decisions without informing the project manager
or other team members
What two actions should project manager take? (Choose two)
Show answerHide answer
Correct answer: C, DReiterate ground rules at the next meeting and ensure that all team members are clear
about these rules.Address the behavioral issue with each team member
Question 10Choose 2
A project manager led the implementation of an electronic invoicing project that has just
been completed. The financial manager communicated that the team discovered three
invoices with errors.
Which two documents should the project manager update as soon as possible? (Choose
two)
Show answerHide answer
Correct answer: A, DIssue logChange log