A project has come to the closing stage. The work is generally finished, and the project
manager wants to commence the closure process for the project. What should the project
manager ensure is in place prior to the closing process?
Show answerHide answer
Correct answer: BThe contractual deliverables of the project have been accepted.
Question 2Choose 1
The project manager of a high-risk project is concerned about a delay in the schedule that
might force the project to ‘move its go-live date. What should the project manager do next?
Show answerHide answer
Correct answer: CCapture the risk in the risk register and monitor it to prevent it from becoming an issue
by taking the proper response action.
Question 3Choose 1
A project manager has been assigned to an important project that will help set the future of
the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project
manager follow this process as well. However, the functional manager has expressed
concerns about the use of new tools on such an important project.
What should the project manager do?
Show answerHide answer
Correct answer: CMake the decision on which project approach to use that would best fit the project.
Question 4Choose 1
An organization is transitioning to an agile approach. At the project's first sprint review, the
product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
Show answerHide answer
Correct answer: AOrganize a sprint retrospective and discuss the issues and how they can be avoided in
the next sprint.
Question 5Choose 1
A project manager has established daily standup meetings with the team during the
execution phase of the project. The project manager has been successful in removing 75%
of the
obstacles reported, but the timeline continues to deviate further each day with no signs of
improvement.
What should the project manager have done to avoid this issue?
Show answerHide answer
Correct answer: APrioritized blockers on the critical path
Question 6Choose 1
A project manager is working in a company that has several global offices. During resource
planning for a new project, the project manager realizes that the company requires projects
to include team members from different continents.
What should the project manager do to ensure a successful project execution?
Show answerHide answer
Correct answer: CConnect with every location and check their preferred methods of communication.
Question 7Choose 1
A project manager has been assigned to a new digital product line, which the company
hopes will boost their revenue. The product is complex and requires customer feedback to
continually refine the product. The project is being handled by a cross-functional agile
team.
What should the project manager do to ensure value is delivered quickly?
Show answerHide answer
Correct answer: APlan the project to deliver value incrementally with regular releases.
Question 8Choose 1
A software delivery project began having technical impediments. The issue may cause a
delay of the deliverables. The technical service team has been working on the issue, but
the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
Show answerHide answer
Correct answer: CUpdate the issue log with the status and priority.
Question 9Choose 2
A key project stakeholder has started to escalate all issues and main requirements to the
project sponsor. The project manager is concemed about the team not receiving direct
communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the
stakeholder? (Choose two)
Show answerHide answer
Correct answer: A, DSchedule regular meetings with the key stakeholder to provide updates and receive
feedback,Promote an adaptive and transparent environment where the team can easily
communicate with the stakeholders.
Question 10Choose 1
A project manager is managing a very important business transformation project. The goal
of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
Show answerHide answer
Correct answer: DIncremental delivery, to ensure that mobile capability is released fast to the users
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.