Question 1 Choose 1
A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?
Show answerHide answer

Correct answer: B The contractual deliverables of the project have been accepted.

Question 2 Choose 1
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?
Show answerHide answer

Correct answer: C Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

Question 3 Choose 1
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?
Show answerHide answer

Correct answer: C Make the decision on which project approach to use that would best fit the project.

Question 4 Choose 1
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?
Show answerHide answer

Correct answer: A Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

Question 5 Choose 1
A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?
Show answerHide answer

Correct answer: A Prioritized blockers on the critical path

Question 6 Choose 1
A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?
Show answerHide answer

Correct answer: C Connect with every location and check their preferred methods of communication.

Question 7 Choose 1
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?
Show answerHide answer

Correct answer: A Plan the project to deliver value incrementally with regular releases.

Question 8 Choose 1
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?
Show answerHide answer

Correct answer: C Update the issue log with the status and priority.

Question 9 Choose 2
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
Show answerHide answer

Correct answer: A, D Schedule regular meetings with the key stakeholder to provide updates and receive feedback,Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

Question 10 Choose 1
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?
Show answerHide answer

Correct answer: D Incremental delivery, to ensure that mobile capability is released fast to the users

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt