A project manager is working with a team that is new to agile. One of the more
influential stakeholders struggles with the nature of agile. The project manager knows that
this
stakeholder is needed as an advocate and wants to do everything possible to make the
stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's
performance?
Show answerHide answer
Correct answer: DEarned value analysis (EVA)
Question 2Choose 1
An equipment vendor will implement a new production line for a client company. The year-
long project will include 2- to 4-month long iterations; however, the client's project manager
has no agile experience.
How should the project manager ensure that the client is effectively represented in the daily
meetings?
Show answerHide answer
Correct answer: CPropose a session tor essential agile Knowledge transfer for the client team to align with
the daily meeting goals
Question 3Choose 1
A company has transitioned and is now delivering projects using a hybrid approach instead
of a predictive approach. The distributed project team's knowledge of agile is varied. The
project manager feels the new methodology will impact the timely delivery of the project.
What should the project manager do?
Show answerHide answer
Correct answer: Bagile tools and techniques used m the defined hybrid methodology for consistent
application by all team members
Question 4Choose 1
A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client's security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client's team. The
project manager does not want to have such an external dependency.
What should the project manager do first?
Show answerHide answer
Correct answer: DDocument the client's responsibility for the integration with the security subsystem.
Question 5Choose 1
A regulatory branch of an environmental government agency has recently placed a ban on
the manufacturing of a specified thickness of plastic packaging products. This ban will take
effect in 12 months. The project manager for a startup firm working in alternative packaging
has been monitoring the progress of this law for a while and. as part of the risk
management, has identified new products that can support a growing customer base.
What should the project manager do next?
Show answerHide answer
Correct answer: CInform management of the new law as an opportunity to expand market share and share
the proposed products
Question 6Choose 1
A company made several changes recently, which resulted in a positive change in
the company culture. A project manager was just assigned to report to a new project
supervisor whose leadership style is about getting things done quickly regardless of
employee
and operational impacts. Some employees are complaining about this.
What should the project manager do?
Show answerHide answer
Correct answer: AClarify expectations by explaining the company culture with the supervisor.
Question 7Choose 1
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this
individual's participation decreases, and activities that they were responsible for are not
being completed within the planned period.
What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a meeting to discuss recent observations with the team member.
Question 8Choose 1
A project manager is managing a government project that targets the development of
small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal
governments will not authorize the training. As a result of the delay, project implementation
is at risk.
What is a probable reason for this?
Show answerHide answer
Correct answer: BThe project did not identify and engage the correct stakeholders.
Question 9Choose 1
During a product demo with key stakeholders, the team identifies that one of the
functionalities failed to perform as expected What should the project manager have the
project team do first to address the issue?
Show answerHide answer
Correct answer: CPerform a root cause analysis
Question 10Choose 1
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
Show answerHide answer
Correct answer: AChange management plan