Question 1 Choose 1
A project manager is working with a team that is new to agile. One of the more influential stakeholders struggles with the nature of agile. The project manager knows that this stakeholder is needed as an advocate and wants to do everything possible to make the stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's performance?
Show answerHide answer

Correct answer: D Earned value analysis (EVA)

Question 2 Choose 1
An equipment vendor will implement a new production line for a client company. The year- long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?
Show answerHide answer

Correct answer: C Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

Question 3 Choose 1
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?
Show answerHide answer

Correct answer: B agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

Question 4 Choose 1
A project team that is very experienced in enterprise resource planning (ERP) systems implementation is currently planning the delivery of a new ERP project. There is a requirement to reuse the client's security subsystem developed by a third party. The client states that integration with the security subsystem must be done by the client's team. The project manager does not want to have such an external dependency.

What should the project manager do first?
Show answerHide answer

Correct answer: D Document the client's responsibility for the integration with the security subsystem.

Question 5 Choose 1
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?
Show answerHide answer

Correct answer: C Inform management of the new law as an opportunity to expand market share and share the proposed products

Question 6 Choose 1
A company made several changes recently, which resulted in a positive change in the company culture. A project manager was just assigned to report to a new project supervisor whose leadership style is about getting things done quickly regardless of employee and operational impacts. Some employees are complaining about this.

What should the project manager do?
Show answerHide answer

Correct answer: A Clarify expectations by explaining the company culture with the supervisor.

Question 7 Choose 1
A key project team member has exhibited high interest in a project. The input from this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?
Show answerHide answer

Correct answer: B Schedule a meeting to discuss recent observations with the team member.

Question 8 Choose 1
A project manager is managing a government project that targets the development of small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?
Show answerHide answer

Correct answer: B The project did not identify and engage the correct stakeholders.

Question 9 Choose 1
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?
Show answerHide answer

Correct answer: C Perform a root cause analysis

Question 10 Choose 1
During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a minimal storage room. The sponsor insists on making this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?
Show answerHide answer

Correct answer: A Change management plan

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt