Question 511 Choose 1
A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?
Show answerHide answer

Correct answer: C Note the reasons for the disagreement and let the team proceed.

Question 512 Choose 1
A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that worked well for previous projects. However, a few team members are not happy with this plan.

What should the project manager have done to avoid this?
Show answerHide answer

Correct answer: B Met with the project team to determine their collaboration needs and identified tools that will work best.

Question 513 Choose 1
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?
Show answerHide answer

Correct answer: D Determine the impact to the project and implement mitigations per the project management plan.

Question 514 Choose 1
A project team is transitioning to agile. During the sprint retrospective, a new member of the team proposed a more structured approach for capturing requirements that would improve clarity and reduce rework. Although the team members are happy to use it, changing the way business requirements are described requires agreement from an influential business manager.

What should the project manager do?
Show answerHide answer

Correct answer: A Contact the business manager and discuss the benefits of the new approach.

Question 515 Choose 1
A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?
Show answerHide answer

Correct answer: B Assess the impact of the change and review the project management plan for next steps.

Question 516 Choose 2
A project manager is reviewing several potential changes to the contract with third-party vendors.

Which two changes could trigger a modification to the vendor contractual obligations?
(Choose 2)
Show answerHide answer

Correct answer: C, E Introducing additional requirements based on new regulationsReplacing a material type based on product availability

Question 517 Choose 1
A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?
Show answerHide answer

Correct answer: D Discuss the team members' concern with the construction manager and seek solutions.

Question 518 Choose 1
A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager do to get this information?
Show answerHide answer

Correct answer: A Organize a one-on-one conversation with each stakeholder.

Question 519 Choose 1
A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.

What should the project manager do?
Show answerHide answer

Correct answer: C Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.

Question 520 Choose 1
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?
Show answerHide answer

Correct answer: C Story points

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt