Question 521 Choose 1
An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.

What should the project manager do to mitigate this risk?
Show answerHide answer

Correct answer: B Schedule an additional interim demo with the product owner.

Question 522 Choose 1
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.

What should the project manager do?
Show answerHide answer

Correct answer: B Arrange for a workshop with the customer to understand the business values expected from the outcomes.

Question 523 Choose 1
At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?
Show answerHide answer

Correct answer: C Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

Question 524 Choose 1
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?
Show answerHide answer

Correct answer: B Perform integrated change control.

Question 525 Choose 1
A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?
Show answerHide answer

Correct answer: B Contact the senior manager and discuss their needs.

Question 526 Choose 1
A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?
Show answerHide answer

Correct answer: A Developed a detailed, phased procurement management plan including all activities required and had the client approve it.

Question 527 Choose 1
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.

What should the project manager do?
Show answerHide answer

Correct answer: A Meet with the project sponsor and key stakeholders to confirm that the information about the forecasted project value is accurate.

Question 528 Choose 1
The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?
Show answerHide answer

Correct answer: A Requirements traceability matrix

Question 529 Choose 1
A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.

What should the project manager do?
Show answerHide answer

Correct answer: A Review the proposed change with the team and consult the project sponsor for approval.

Question 530 Choose 2
A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

Which first two actions should the project manager perform? (Choose 2)
Show answerHide answer

Correct answer: B, D Perform a risk identification process with the project team.Consult with the project stakeholders and evaluate the impact.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt