A solution designer in an agile team often passes the design information to team members
without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
Show answerHide answer
Correct answer: BReview the process that resulted in this situation.
Question 2Choose 1
project manager for a defense software application has a culturally and gender-diverse
team with a short project time line Considering the project will be stressful what skill should
the project manager use to monitor the team's performance?
Show answerHide answer
Correct answer: CEmotional intelligence
Question 3Choose 1
A few virtual team members are located in a region that generally has good internet
connectivity. However, they frequently experience connectivity
issues joining team calls during the day.
What should the project manager do?
Show answerHide answer
Correct answer: DDetermine what the problem is and develop an action plan.
Question 4Choose 1
A project manager works for a large global company. The project manager is leading a
project where the expected business value is to improve the company's image and
reputation. During the project's closing phase, the project manager realizes that there is still
a negative perception about the company's brand.
What should the project manager have done to prevent this?
Show answerHide answer
Correct answer: AMonitored progress in achieving the business value throughout the project
Question 5Choose 1
A project manager is assigned to a project that has a tight schedule. Due to recent market
changes the marketing team has identified that a few features that were initially in the
scope are no longer required
What should the project manager do?
Show answerHide answer
Correct answer: DReview the change request with the project stakeholders and evaluate the impact of the
scope reduction
Question 6Choose 1
A final iteration is underway and a project team is about to complete development Planning
tot the product release is about to start. One stakeholder raised a concern about the
product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
Show answerHide answer
Correct answer: AAssess the business value impact and review the product roadmap to include any
changes
Question 7Choose 1
A project manager works at an organization that intends to use an agile delivery approach,
The product owner asks the project manager what the benefit of agile delivery is from a
project evaluation perspective?
How should the project manager reply to the product owner?
Show answerHide answer
Correct answer: AThe functionality is delivered early; therefore, more value is delivered.
Question 8Choose 1
A senior-level executive approached the project manager of a highly visible project that is
currently in the execution phase. The executive indicated that they do not support the
project
and will be actively trying to prevent its success by reailocating key team members to
another critical project.
What should the project manager do?
Show answerHide answer
Correct answer: BWork with the project sponsor to determine an appropriate response.
Question 9Choose 1
A servant leader is about to start a confidential agile research project. A high risk has been
identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
Show answerHide answer
Correct answer: AInclude this restriction as a ground rule and ensure all team members are familiar with it
by reviewing the ground rules at the end of everyiteration.
Question 10Choose 1
A project manager is a part of the project management office (PMO) and Is tasked with
finding a reputable vendor to provide on-site support for their project. The project sponsor
stresses the urgency of the need and suggests using a vendor they know to provide the
support.
What should the project manager do given the urgency?
Show answerHide answer
Correct answer: DFollow the company's standard vendor selection criteria process,