A project team member just informed the project manager that the license for the software
that the team uses to perform calculations has just expired. As a result, the team cannot
continue with their project tasks.
What should the project manager do first?
Show answerHide answer
Correct answer: BMeet with the IT team to evaluate how fast the software license can be renewed.
Question 492Choose 1
Some of the more experienced members of a project team have complained about the
project manager. The senior project team members feel that the project manager is
micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
Show answerHide answer
Correct answer: BAdjust the project manager's management style to better fit senior team members.
Question 493Choose 1
A project manager is leading an engineering project. The project manager must obtain
some certifications before mass production, which is scheduled in 3 months. The
certification process will require at least 6 months.
What should the project manager do next?
Show answerHide answer
Correct answer: DAssess and evaluate the certification process and understand the best and worst case
scenarios.
Question 494Choose 1
A project manager who recently joined the company has been assigned to manage a
software project for a major recurring customer. What should the project manager do to
enhance the budget estimations for the project?
Show answerHide answer
Correct answer: BReview budget-related lessons learned from similar projects.
Question 495Choose 1
A project manager has been assigned to a project after the charter has been approved.
While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?
Show answerHide answer
Correct answer: DImmediately discuss this with the project sponsor and request to revisit the budget to
ensure its accuracy.
Question 496Choose 1
A team member has experienced personal conflicts on past projects, making them nervous
about working on the current project. The project
manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
Show answerHide answer
Correct answer: CAdvise the team member to focus on the current project and consider the past conflicts
as lessons learned.
Question 497Choose 1
A primary stakeholder is unable to join the project status meetings consistently. The project
manager has been communicating with this stakeholder informally and regularly
to ensure that the stakeholder is up to date on the project. However. the project manager
has recently resigned and will not be meeting with the new project manager prior to departure.
How should the project manager ensure that the new project manager continues to update
this particular stakeholder?
Show answerHide answer
Correct answer: BUpdate the stakeholder engagement plan with the specific communication needs for the
stakeholder.
Question 498
In an effort to modernize the technology for a project, the project manager has been
discussing risk prioritization with the project team. The project manager determines that
additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
Show answerHide answer
Explanation
Question 499Choose 3
An organization's human resources (HR) department wants to create a high-performing
team and implement a project that includes job grading, organizational restructuring, and
soft skills training.
To ensure the quality of the project deliverable, which three actions should the project
manager take? (Choose 3)
Show answerHide answer
Correct answer: A, C, DCollect feedback and conduct surveys and questionnaires.Document quality gaps and analyze them for continuous improvement.Develop a proper quality management plan with measurable metrics.
Question 500Choose 1
A project manager is managing a mobile application development project when one of the
experienced team members starts missing deadlines. The delays will impact project implementation.
What should the project manager do next?
Show answerHide answer
Correct answer: AMeet with the team member to understand their concerns and/or issues.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.