A subject matter expert (SME) external to the project team provides a suggestion that will
save the project delivery time. This SME has available
time to support the project, but was not planned to be involved in the current agile iteration.
What should the project manager do?
Show answerHide answer
Correct answer: BAsk the existing team members to collaborate with the SME and complete the activity.
Question 482Choose 1
A project manager is working on a unique project that is dissimilar to the project nature of
the organization. The project manager is tailoring the artifacts for this new project.
Who should determine which artifacts should be used in the project?
Show answerHide answer
Correct answer: DThe project manager and the project management team should select the appropriate
artifacts for use in the specific project.
Question 483Choose 1
A project with a geographically distributed team is ending its first iteration out of eight.
During the daily meetings, the project manager realizes that some team members are not
engaging in the discussion.
What should the project manager do?
Show answerHide answer
Correct answer: AConduct a team activity to determine the reasons for this situation.
Question 484Choose 1
A highly critical project is in jeopardy due to missing professional resources. What should
the newly assigned project manager do first?
Show answerHide answer
Correct answer: CDetermine the possibility for team members to split up the required tasks.
Question 485Choose 1
A project manager works for a company that has a reputation of delivering environmentally
sustainable projects. During the half-yearly review of the project, the project manager
raises serious concerns with
the project sponsor regarding the project's viability and success. There are some
stakeholders who oppose this project on the grounds of compromising land erosion.
What should the project manager do?
Show answerHide answer
Correct answer: APropose to close the project because it no longer fits the business values of the
organization.
Question 486Choose 1
After sending an on-site meeting invitation to seven people for the kick-off meeting of a
project, a key stakeholder declines because they will be at another location for the rest of
the month.
What should the project manager do?
Show answerHide answer
Correct answer: AMake arrangements for the stakeholder to join the kick-off meeting virtually.
Question 487Choose 1
A project manager is assigned to a major construction project. The project is critical to the
city's population, and especially to the local government
official who committed to delivering the project on time as an election promise. A new
project sponsor has been assigned and wants to include
aspects that the previous project sponsor did not support.
What should the project manager do next?
Show answerHide answer
Correct answer: AMeet with the new project sponsor to review the current project scope and the requested
changes.
Question 488Choose 1
A company has appointed a supplier to deliver software and has assigned an internal
project manager. The supplier states that no technical development or testing is required
from the customer. The project manager would like to confirm this with all of the
stakeholders.
What should the internal project manager do first?
Show answerHide answer
Correct answer: BHost an alignment session with stakeholders to formalize the project requirements.
Question 489Choose 1
During a project, the project manager finds an opportunity to reduce the project cost by
completing a deliverable ahead of schedule with a minimal
impact on project resources. However, the client has only been focused on the next
milestone.
How should the project manager approach this situation?
Show answerHide answer
Correct answer: CReview the change management plan to discuss early benefits realization with the
client.
Question 490Choose 1
A project manager has been assigned to lead an IT project to store information on sold
lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of
greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
Show answerHide answer
Correct answer: CReview the list of risks to verify that this issue was considered and execute the detailed
action plan.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.