Question 481 Choose 1
A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?
Show answerHide answer

Correct answer: B Ask the existing team members to collaborate with the SME and complete the activity.

Question 482 Choose 1
A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?
Show answerHide answer

Correct answer: D The project manager and the project management team should select the appropriate artifacts for use in the specific project.

Question 483 Choose 1
A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion.

What should the project manager do?
Show answerHide answer

Correct answer: A Conduct a team activity to determine the reasons for this situation.

Question 484 Choose 1
A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?
Show answerHide answer

Correct answer: C Determine the possibility for team members to split up the required tasks.

Question 485 Choose 1
A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?
Show answerHide answer

Correct answer: A Propose to close the project because it no longer fits the business values of the organization.

Question 486 Choose 1
After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?
Show answerHide answer

Correct answer: A Make arrangements for the stakeholder to join the kick-off meeting virtually.

Question 487 Choose 1
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support.

What should the project manager do next?
Show answerHide answer

Correct answer: A Meet with the new project sponsor to review the current project scope and the requested changes.

Question 488 Choose 1
A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.

What should the internal project manager do first?
Show answerHide answer

Correct answer: B Host an alignment session with stakeholders to formalize the project requirements.

Question 489 Choose 1
During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal impact on project resources. However, the client has only been focused on the next milestone.

How should the project manager approach this situation?
Show answerHide answer

Correct answer: C Review the change management plan to discuss early benefits realization with the client.

Question 490 Choose 1
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?
Show answerHide answer

Correct answer: C Review the list of risks to verify that this issue was considered and execute the detailed action plan.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt