Question 471 Choose 1
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?
Show answerHide answer

Correct answer: C Incorrect communication techniques applied during implementation

Question 472 Choose 1
An agile team has released the second version of its product, but the feedback is that the software has many bugs that compromise the user experience. What should the project manager do?
Show answerHide answer

Correct answer: A Facilitate the next retrospective meeting, focusing the team on analyzing root causes and proposing solutions.

Question 473 Choose 1
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?
Show answerHide answer

Correct answer: A Perform a cost-benefit analysis to evaluate using the Point B option.

Question 474 Choose 1
A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?
Show answerHide answer

Correct answer: A Explain to the team that open discussions are needed but remind the team to follow the ground rules.

Question 475 Choose 1
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?
Show answerHide answer

Correct answer: C Kanban board

Question 476 Choose 1
A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?
Show answerHide answer

Correct answer: C Review the options and possible solutions with the project team.

Question 477 Choose 1
In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project manager do next?
Show answerHide answer

Correct answer: D Produce a value-added product for the customer in each phase of the project.

Question 478 Choose 1
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
Show answerHide answer

Correct answer: C Organize more frequent sprint reviews with a broader audience.

Question 479 Choose 1
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.

What should the project manager do to resolve this conflict?
Show answerHide answer

Correct answer: D Communicate with the resource on the roles and responsibilities of this project.

Question 480 Choose 1
A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the company's core working hours begin at 9:00 a.m.

What should the project manager have done to prevent this situation?
Show answerHide answer

Correct answer: C Analyzed the boundaries of the negotiations for agreement

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt