A project manager assigned team members to work in pairs on a large amount of technical
reports. At times, the project manager noticed that important information was not
shared properly among the team. This has caused delivery delays and, ultimately, the
failure to complete the project.
What is the root cause of this issue?
Show answerHide answer
Correct answer: CIncorrect communication techniques applied during implementation
Question 472Choose 1
An agile team has released the second version of its product, but the feedback is that the
software has many bugs that compromise the user experience. What should the
project manager do?
Show answerHide answer
Correct answer: AFacilitate the next retrospective meeting, focusing the team on analyzing root causes
and proposing solutions.
Question 473Choose 1
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,
Point A, which requires a significant cable length. The construction team found that the
power could be connected to Point B and save money.
What should the project manager do next?
Show answerHide answer
Correct answer: APerform a cost-benefit analysis to evaluate using the Point B option.
Question 474Choose 1
A member of the project team always extends discussion topics, taking more time than
necessary during project team meetings. Other team members feel this member is not
being considerate of their time.
What should the project manager do?
Show answerHide answer
Correct answer: AExplain to the team that open discussions are needed but remind the team to follow the
ground rules.
Question 475Choose 1
A team decides to adopt an agile approach for their new project. During a sprint, the project
manager realizes that there is a need to show progress and optimize the collaboration
among teams.
Which tool should the project manager use?
Show answerHide answer
Correct answer: CKanban board
Question 476Choose 1
A project is starting its sixth iteration out seven. During the daily meeting, a team member
explains that a key function will take longer to complete than originally anticipated.
What should the project manager do?
Show answerHide answer
Correct answer: CReview the options and possible solutions with the project team.
Question 477Choose 1
In the initiating phase of a project, the project manager and team members are prioritizing
the product backlog along with the product owner. What should the project
manager do next?
Show answerHide answer
Correct answer: DProduce a value-added product for the customer in each phase of the project.
Question 478Choose 1
An organization that embraced agile a couple of years ago is looking for a more efficient
way to ensure that the increments produced in each sprint meet the end users’ quality
requirements. What should the project lead recommend?
Show answerHide answer
Correct answer: COrganize more frequent sprint reviews with a broader audience.
Question 479Choose 1
A project manager recently finished a project and started managing a new project with a
different supervisor. As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately
begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?
Show answerHide answer
Correct answer: DCommunicate with the resource on the roles and responsibilities of this project.
Question 480Choose 1
A project manager agreed to a team member's request to have an alternative working
schedule whereby they begin working at 12:00 p.m. each
day. This arrangement has worked well for the project, but has recently been scrutinized by
members from other project teams because the
company's core working hours begin at 9:00 a.m.
What should the project manager have done to prevent this situation?
Show answerHide answer
Correct answer: CAnalyzed the boundaries of the negotiations for agreement