A company is implementing a growth strategy by constructing a new production facility,
which will soon move into the operation phase. Although a governance policy was already
in place, the company must comply with new financial regulations that have been recently
implemented. Compliance with the regulations will cause a major change
in project scope.
How should the project manager respond to this requirement?
Show answerHide answer
Correct answer: BPerform an analysis to assess the impact on the project.
Question 462Choose 1
A project manager is working on an agile project in a changing business environment. The
project sponsor is worried about benefits realization
and asks the project manager to pay attention to changes that can affect the project.
Which action should the project manager take to identify changes that may affect the
product?
Show answerHide answer
Correct answer: CTake action to reprioritize the backlog after every iteration to evaluate if user stories are
still valuable to the business.
Question 463Choose 1
A project for a financial organization is in the proposal phase for the selection of a software
tool. There have been conflicting opinions on the software that was ranked in the selection.
After analyzing the issue, the project manager realizes that two out of the eight teams have
concerns about the tool's scalability to support their business needs.
How should the project manager resolve this conflict and reach a consensus?
Show answerHide answer
Correct answer: DDiscuss the outcome of the proposal process and the ranking, then influence the team
for acceptance.
Question 464Choose 1
A project manager is working on a complex project with a high degree of change. What
strategy should the project manager use to ensure a
successful project completion?
Show answerHide answer
Correct answer: CIncrease the active engagement and participation of key stakeholders.
Question 465Choose 1
A project team is working on the design of a solution for a complex project. Due to a lack of
clarity of the customer's requirements, daily meetings
were agreed upon between the team and the customer. There are a few external
contractors in the project who do not agree with this idea as they
feel it is a waste of time.
What should the project manager do?
Show answerHide answer
Correct answer: AWelcome and involve the contractors as part of the project team.
Question 466Choose 1
A company just started managing a project using an agile approach. Due to this change,
the general manager is worried about the scope definition process for upcoming projects.
What should the project manager do to ensure the project scope is completely defined?
Show answerHide answer
Correct answer: BAsk for a budget increase to implement a double-check process to ensure every
business need is included in the requirements
Question 467Choose 1
Anew major road project is starting, and the contractor has contractually committed to
submitting regular status reports and participating in integration meetings. Halfway through
the project life cycle, the contractor stops participating in meetings and submitting reports,
stating these items consume too much time.
What should the project manager do first?
Show answerHide answer
Correct answer: CRemind the contractor that they committed to attending meetings and submitting reports
per the contract.
Question 468Choose 1
A project manager is implementing a project similar to a previous one that required strict
adherence to occupational health and safety (OHS). Both projects are for the same client
whose business environment is highly regulated. However, this time the client does not
appear to be concerned about OHS requirements.
What should the project manager do first?
Show answerHide answer
Correct answer: BDiscuss the OHS requirements with the client.
Question 469Choose 1
During a monthly review meeting, a high-performing team member raised a concern about
the quality feedback mechanism. The team member expressed that they are not able to
deliver high-quality output.
What should the project manager do first?
Show answerHide answer
Correct answer: DDiscuss this with the team and review the quality process.
Question 470Choose 1
A project requires the procurement of a large amount of equipment that needs to be on-site
before any other activity can begin. The procurement department has a lengthy approval
process.
What should the project manager do?
Show answerHide answer
Correct answer: AWork with the procurement team to find alternative options.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.