Question 461 Choose 1
A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope.

How should the project manager respond to this requirement?
Show answerHide answer

Correct answer: B Perform an analysis to assess the impact on the project.

Question 462 Choose 1
A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?
Show answerHide answer

Correct answer: C Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

Question 463 Choose 1
A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?
Show answerHide answer

Correct answer: D Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.

Question 464 Choose 1
A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a successful project completion?
Show answerHide answer

Correct answer: C Increase the active engagement and participation of key stakeholders.

Question 465 Choose 1
A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they feel it is a waste of time.

What should the project manager do?
Show answerHide answer

Correct answer: A Welcome and involve the contractors as part of the project team.

Question 466 Choose 1
A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?
Show answerHide answer

Correct answer: B Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

Question 467 Choose 1
Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.

What should the project manager do first?
Show answerHide answer

Correct answer: C Remind the contractor that they committed to attending meetings and submitting reports per the contract.

Question 468 Choose 1
A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.

What should the project manager do first?
Show answerHide answer

Correct answer: B Discuss the OHS requirements with the client.

Question 469 Choose 1
During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?
Show answerHide answer

Correct answer: D Discuss this with the team and review the quality process.

Question 470 Choose 1
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?
Show answerHide answer

Correct answer: A Work with the procurement team to find alternative options.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt