A team is focusing on quickly developing and shipping new product features due to very
aggressive market demands. The team is setting aside long-term work not directly related
to the current business objective, which affects product performance and generates more
customer support requests.
How can the team minimize the impact of the reduced focus on quality?
A project manager is assigned to work on a complex and innovative project. The
technology being used and developed is new and complicated, and most of the
stakeholders are unfamiliar with it.
Which approach should the project manager use as a servant leader?
Show answerHide answer
Correct answer: BAllocate resources to provide training about the new technology to the stakeholders.
Question 453Choose 1
During the execution phase of a project, a new department has been created in the
company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
Show answerHide answer
Correct answer: CPerform a stakeholder analysis and update the communications management plan to
reflect the new situation.
Question 454Choose 1
A project manager schedules virtual daily standup meetings for a project, but half of the
team members regularly join late or miss the meeting all together. What should the project
manager do?
Show answerHide answer
Correct answer: DAgree on a new time and reschedule the daily standups.
Question 455Choose 1
A company is transitioning projects from a predictive to an agile approach. The CFO is
concerned that one of the agile projects has an important feature for the financial
department that is being delayed for a later iteration.
What should the project manager do to clarify the situation?
Show answerHide answer
Correct answer: BClarify with the CFO that the prioritization process is based on business value.
Question 456Choose 1
A customer is concerned with the quality of the product delivery, as the production
deployment is approaching. What should the project manager do next to ensure
acceptance of the deliverables?
Show answerHide answer
Correct answer: CReview the approved exit criteria for the product.
Question 457Choose 1
In the middle of a software development project, the lead design programmer accepted an
offer from a competitor. The project manager needs to find a replacement to meet an
upcoming milestone.
What should the project manager do?
Show answerHide answer
Correct answer: AConsult the risk response plan.
Question 458Choose 1
An agile team has completed five sprints. The final product is expected to be delivered in
another three sprints. The project manager receives a call from the technical resource
manager that one of the developers must take leave for the next 4 weeks, with no
temporary replacement available. This is going to significantly impact the deliverable.
What should the project manager do?
Show answerHide answer
Correct answer: APerform an impact analysis, readjust the schedule as needed, and communicate the
changes to the customer.
Question 459Choose 1
A project manager is leading a project in an organization that has a functional structure.
The project manager has been informed by the team that the tasks related to the purchase
of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
Show answerHide answer
Correct answer: CMeet with the purchasing manager to find the source of the delays and agree on a
purchasing schedule.
Question 460Choose 1
A project manager is leading a long-term project, executed in stages, to set up a complex
communications network in many rural areas. The project is being executed in stages.
What should the project manager do to ensure that monetized business value is generated
as planned?
Show answerHide answer
Correct answer: DEvaluate the generated benefits at project milestones against the project business plan