Question 451 Choose 1
A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.

How can the team minimize the impact of the reduced focus on quality?
Show answerHide answer

Correct answer: C Consider implementing test-driven methodology.

Question 452 Choose 1
A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.

Which approach should the project manager use as a servant leader?
Show answerHide answer

Correct answer: B Allocate resources to provide training about the new technology to the stakeholders.

Question 453 Choose 1
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to be involved in the regular project communications and reporting cycles.

What should the project manager do?
Show answerHide answer

Correct answer: C Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

Question 454 Choose 1
A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?
Show answerHide answer

Correct answer: D Agree on a new time and reschedule the daily standups.

Question 455 Choose 1
A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial department that is being delayed for a later iteration.

What should the project manager do to clarify the situation?
Show answerHide answer

Correct answer: B Clarify with the CFO that the prioritization process is based on business value.

Question 456 Choose 1
A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?
Show answerHide answer

Correct answer: C Review the approved exit criteria for the product.

Question 457 Choose 1
In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?
Show answerHide answer

Correct answer: A Consult the risk response plan.

Question 458 Choose 1
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.

What should the project manager do?
Show answerHide answer

Correct answer: A Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

Question 459 Choose 1
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?
Show answerHide answer

Correct answer: C Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

Question 460 Choose 1
A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.

What should the project manager do to ensure that monetized business value is generated as planned?
Show answerHide answer

Correct answer: D Evaluate the generated benefits at project milestones against the project business plan

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt