Question 441 Choose 1
A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.

How should the project manager address the customer's requests?
Show answerHide answer

Correct answer: D Explain to the customer that the project has been completed and enhancements will follow the change management process.

Question 442 Choose 1
A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.

How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
Show answerHide answer

Correct answer: B Estimate the costs at the work package level and add those costs to calculate the total cost of the project and compare it to the allocated budget.

Question 443 Choose 1
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
Show answerHide answer

Correct answer: A Reach an agreement with the team on how to handle the situation.

Question 444 Choose 1
A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?
Show answerHide answer

Correct answer: D Estimate the impact and consult with the product owner.

Question 445 Choose 1
A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?
Show answerHide answer

Correct answer: D Ensure that the reports comply with the communications management plan.

Question 446 Choose 1
A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems.

What should the project manager do next?
Show answerHide answer

Correct answer: C Help the customer find an alternative location to start the training.

Question 447 Choose 1
At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?
Show answerHide answer

Correct answer: B Probabilistic analysis was used to develop the budget to address future uncertainties.

Question 448 Choose 3
A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.

Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)
Show answerHide answer

Correct answer: A, B, E Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.Schedule shadowing sessions among team members to facilitate team learning.

Question 449 Choose 1
A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?
Show answerHide answer

Correct answer: D Use metrics to track the cost performance

Question 450 Choose 1
A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
Show answerHide answer

Correct answer: D Assess the possible impact of the raw material shortage on the project.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt