A project has recently completed its production go-live, meeting the project's completion
requirements in accordance with the scope document. However, the customer has been
requesting a number of significant project enhancements.
How should the project manager address the customer's requests?
Show answerHide answer
Correct answer: DExplain to the customer that the project has been completed and enhancements will
follow the change management process.
Question 442Choose 1
A project manager is planning a project with multiple work packages. Each work package
has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to
cover the resource costs of the project?
Show answerHide answer
Correct answer: BEstimate the costs at the work package level and add those costs to calculate the total
cost of the project and compare it to the allocated budget.
Question 443Choose 1
In the middle of an iteration, an agile team working on the development of a new product
was notified that an important team member will leave the project for a few weeks due to
some urgent personal issues. What should the project manager do regarding the activities
that were the responsibility of this team member?
Show answerHide answer
Correct answer: AReach an agreement with the team on how to handle the situation.
Question 444Choose 1
A project is ending its fifth out of six iterations. During the iteration review, a customer adds
a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?
Show answerHide answer
Correct answer: DEstimate the impact and consult with the product owner.
Question 445Choose 1
A key stakeholder who is highly involved in the project claims that the reports sent by the
project team are inadequate. What should the project manager do first?
Show answerHide answer
Correct answer: DEnsure that the reports comply with the communications management plan.
Question 446Choose 1
A project manager assigned to an education project needs to train a workforce in
application development. The customer is responsible for
providing the training center, and the deadline to start the first training is in 2 weeks. The
customer calls to say that the center will not be available
in 2 weeks due to some unforeseen problems.
What should the project manager do next?
Show answerHide answer
Correct answer: CHelp the customer find an alternative location to start the training.
Question 447Choose 1
At the end of a project's initiation phase, the budget was developed and sent to the
approval board. During the approval meeting, one of the key stakeholders asked how the
budget was developed for future uncertainties.
How should the project manager reply?
Show answerHide answer
Correct answer: BProbabilistic analysis was used to develop the budget to address future uncertainties.
Question 448Choose 3
A new project team consists of team members from different departments who have
varying levels of experience and different areas of expertise.
Which three approaches should the project manager take in order to facilitate knowledge
sharing? (Choose 3)
Show answerHide answer
Correct answer: A, B, EArrange a daily learning session for project team members during lunch to facilitate
knowledge transfer.Allow each team member time in the retrospective sessions to share a little bit about
their role and areas of knowledge.Schedule shadowing sessions among team members to facilitate team learning.
Question 449Choose 1
A project manager is looking for ways to keep the budget on track throughout the project life cycle.
What should the project manager do to ensure that happens?
Show answerHide answer
Correct answer: DUse metrics to track the cost performance
Question 450Choose 1
A project manager was informed by their supplier that there will be an upcoming raw
material shortage due to a regulatory change. What should the project manager do?
Show answerHide answer
Correct answer: DAssess the possible impact of the raw material shortage on the project.