A project manager is well informed on the industry standards of the organization and
believes that they are not reflected in the project deliverables. What should the project
manager review next?
Show answerHide answer
Correct answer: BQuality management plan
Question 432Choose 1
A customer reviewed the plan for a project with high uncertainty. The customer expressed
concerned about the work requiring SO many iterations with a risk of not reaching the
mandatory delivery date.
Which approach should the project manager use in this situation?
Show answerHide answer
Correct answer: AHybrid approach
Question 433Choose 1
A startup company has just appointed a CEO that has no prior project experience. The
CEO wants to execute projects with their own resources
and has appointed a project manager.
What should the project manager recommend that the CEO do first?
Show answerHide answer
Correct answer: CCreate a framework to support project success.
Question 434Choose 1
A project manager is leading a large public project that will have a high impact on the
town's citizens. How should the project manager define the different requirements?
Show answerHide answer
Correct answer: CAnalyze the interests and influence of stakeholders and evaluate their requirements.
Question 435Choose 1
A project manager is managing a large project. During a review meeting, the project
manager discovers that one of the team members who use to be a high performer was not
able to complete their work on time.
What should the project manager do?
Show answerHide answer
Correct answer: ATalk to the team member to determine why their performance changed.
Question 436Choose 1
A project manager is in a cross-functional agile team. The project manager has been
assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to
meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
Show answerHide answer
Correct answer: AWork with the stakeholders to create a prioritized backlog and release a roadmap.
Question 437Choose 1
A company that uses a predictive approach and operates in a highly regulated market is
losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.
What approach should the project manager propose?
Show answerHide answer
Correct answer: DPropose a hybrid approach, leveraging the benefits of an agile approach while
respecting some aspects of the company’s industry.
Question 438Choose 1
A company plans to initiate a project involving a new technology. Approval for the project is
required. What should the project manager do?
Show answerHide answer
Correct answer: DIdentify the risks in implementing the new technology.
Question 439Choose 1
A team member who is working on a critical project deliverable reported that their computer
is not working. The IT department says that due to a high workload, they will not
be able to provide assistance for 1 week.
How should the project manager address this situation?
Show answerHide answer
Correct answer: CExplore options with the IT department to expedite the necessary repairs based on
criticality of the project.
Question 440Choose 1
A project team is executing a megaproject, and several contract requirements have been
identified. In the planning phase, the project team agreed that a contract would be
required 3 months prior to the project's finish date. During project execution, it was
determined that the contract was required immediately.
What should project manager do?
Show answerHide answer
Correct answer: BRequest the team to initiate a change request to execute the contract.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.