Free PMP mock exam questions 431–440, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Free PMP questions

431–440 of 636 free
Question 431 Choose 1
A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?
Show answerHide answer

Correct answer: B Quality management plan

Question 432 Choose 1
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.

Which approach should the project manager use in this situation?
Show answerHide answer

Correct answer: A Hybrid approach

Question 433 Choose 1
A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources and has appointed a project manager.

What should the project manager recommend that the CEO do first?
Show answerHide answer

Correct answer: C Create a framework to support project success.

Question 434 Choose 1
A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?
Show answerHide answer

Correct answer: C Analyze the interests and influence of stakeholders and evaluate their requirements.

Question 435 Choose 1
A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?
Show answerHide answer

Correct answer: A Talk to the team member to determine why their performance changed.

Question 436 Choose 1
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months.

What should the project manager do to align stakeholders’ needs and expectations?
Show answerHide answer

Correct answer: A Work with the stakeholders to create a prioritized backlog and release a roadmap.

Question 437 Choose 1
A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?
Show answerHide answer

Correct answer: D Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

Question 438 Choose 1
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
Show answerHide answer

Correct answer: D Identify the risks in implementing the new technology.

Question 439 Choose 1
A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.

How should the project manager address this situation?
Show answerHide answer

Correct answer: C Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

Question 440 Choose 1
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?
Show answerHide answer

Correct answer: B Request the team to initiate a change request to execute the contract.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt