A project team is transitioning from a predictive to an agile approach. The project manager
is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
Show answerHide answer
Correct answer: CEngage the operation teams in the retrospectives and demo sessions and incorporate
their feedback on project activities.
Question 422Choose 1
A multiyear resource constraint project is midway through the execution phase. During a
progress update meeting, it has been determined that there might be a schedule delay to
deliver the project. The project manager has observed that all of the team members are
working hard and lots of deliverables have already been completed.
What should the project manager do immediately about this situation?
Show answerHide answer
Correct answer: AAsk the project planner to identify the critical path and respective delayed activities, and
then investigate the reasons for the delay.
Question 423Choose 1
A project manager is leading a hybrid project that is building an app for a travel industry
startup. Due to unforeseen events, the features and the overall solution will not be useable
by many customers due to new travel restrictions.
What should the project manager do first?
Show answerHide answer
Correct answer: CAssess the environmental changes and recommend a pivot for the project.
Question 424Choose 1
An experienced project manager is leading an enthusiastic team but realizes the team
lacks the experience to complete the job successfully. What should the project manager do
to reduce the risk of project failure?
Show answerHide answer
Correct answer: DProvide team members with the necessary coaching and mentoring.
Question 425Choose 1
During the execution of a project, a key stakeholder complains to the project manager
about recent communications.
The key stakeholder explains that the relevant information from the project team was
incomplete and late. As a result, the key stakeholder is beginning to disengage from the
project.
What should the project manager do?
Show answerHide answer
Correct answer: DUpdate the communications management plan to fulfill the key stakeholder's
expectations about relevant information.
Question 426Choose 1
A protect team is working remotely on a solution The client wants the solution as soon as
possible and is uncomfortable because the team members are not colocated In addition the
client expressed concerns about the understanding of the project context and the team's
decision-making process
What should the project manager do?
Show answerHide answer
Correct answer: AUpdate the communications management plan to satisfy the client's request
Question 427Choose 1
A project schedule risk has turned into an issue. The project manager foresees delays in
project execution.
What should the project manager do to resolve the issue?
Show answerHide answer
Correct answer: DWork with relevant stakeholders to determine possible solutions.
Question 428Choose 1
A project manager is reviewing a draft of the project charter with key stakeholders. During
the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?
Show answerHide answer
Correct answer: DContinue the meeting and use facilitation techniques to improve communication within
the team.
Question 429Choose 1
In a daily standup meeting, a developer indicates that a backlog item will not be delivered
because they need to take an unexpected leave for the next couple of days. The backlog
item is a prerequisite for a feature expected by users in the next sprint review.
What should the project lead do?
Show answerHide answer
Correct answer: CWork with the product owner to change the priorities in the sprint backlog.
Question 430Choose 1
A client wants to create an innovative software for the travel industry using an agile
approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
Show answerHide answer
Correct answer: DWork with the team to understand their views and add the appropriate dependencies
and risks.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.