Question 421 Choose 1
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?
Show answerHide answer

Correct answer: C Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

Question 422 Choose 1
A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?
Show answerHide answer

Correct answer: A Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

Question 423 Choose 1
A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?
Show answerHide answer

Correct answer: C Assess the environmental changes and recommend a pivot for the project.

Question 424 Choose 1
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully. What should the project manager do to reduce the risk of project failure?
Show answerHide answer

Correct answer: D Provide team members with the necessary coaching and mentoring.

Question 425 Choose 1
During the execution of a project, a key stakeholder complains to the project manager about recent communications.

The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?
Show answerHide answer

Correct answer: D Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.

Question 426 Choose 1
A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?
Show answerHide answer

Correct answer: A Update the communications management plan to satisfy the client's request

Question 427 Choose 1
A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?
Show answerHide answer

Correct answer: D Work with relevant stakeholders to determine possible solutions.

Question 428 Choose 1
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?
Show answerHide answer

Correct answer: D Continue the meeting and use facilitation techniques to improve communication within the team.

Question 429 Choose 1
In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.

What should the project lead do?
Show answerHide answer

Correct answer: C Work with the product owner to change the priorities in the sprint backlog.

Question 430 Choose 1
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?
Show answerHide answer

Correct answer: D Work with the team to understand their views and add the appropriate dependencies and risks.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt