PMP Mock Exam Page 42

Project Management Professional (PMP) July 2026 Update

Free PMP mock exam questions 411–420, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Free PMP questions

411–420 of 636 free
Question 411 Choose 1
An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.

What should the project manager do next?
Show answerHide answer

Correct answer: A Incorporate and prioritize the risks in the risk register according to impact.

Question 412 Choose 1
An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?
Show answerHide answer

Correct answer: B Schedule virtual sessions with the specialist to guide the team in completing the activity.

Question 413 Choose 1
A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price.

What should have been done differently to avoid this scenario?
Show answerHide answer

Correct answer: A A minimum viable product (MVP) should have been released to get feedback from the market.

Question 414 Choose 1
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
Show answerHide answer

Correct answer: B By focusing on the delivery of incremental working products lo the customer

Question 415 Choose 1
A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?
Show answerHide answer

Correct answer: A Support the team in identifying the area of development and address the gap.

Question 416 Choose 1
A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: B Allocated proper resources for training on BMS in the project plan

Question 417 Choose 1
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?
Show answerHide answer

Correct answer: A Re-visit the project charter and seek other alternatives.

Question 418 Choose 1
A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?
Show answerHide answer

Correct answer: C Work breakdown structure (WBS)

Question 419 Choose 1
A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.

What should the project manager do?
Show answerHide answer

Correct answer: C Set up a team alignment session to discuss the remaining work and contract with the team.

Question 420 Choose 2
In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)
Show answerHide answer

Correct answer: A, C Request the CEO to assign some of the functional team members to work on the presentation.Determine a new target completion date for the project based on the redirection of the team.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt