What should the project manager do next?
Show answerHide answer
Correct answer: A Incorporate and prioritize the risks in the risk register according to impact.
Project Management Professional (PMP) July 2026 Update
Free PMP mock exam questions 411–420, each with the answer and an explanation.
20 questions · 26 minutes · free, no sign-up
Correct answer: A Incorporate and prioritize the risks in the risk register according to impact.
Correct answer: B Schedule virtual sessions with the specialist to guide the team in completing the activity.
Correct answer: A A minimum viable product (MVP) should have been released to get feedback from the market.
Correct answer: B By focusing on the delivery of incremental working products lo the customer
Correct answer: A Support the team in identifying the area of development and address the gap.
Correct answer: B Allocated proper resources for training on BMS in the project plan
Correct answer: A Re-visit the project charter and seek other alternatives.
Correct answer: C Work breakdown structure (WBS)
Correct answer: C Set up a team alignment session to discuss the remaining work and contract with the team.
Correct answer: A, C Request the CEO to assign some of the functional team members to work on the presentation.Determine a new target completion date for the project based on the redirection of the team.
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PMP mock exam