Question 401 Choose 1
During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project manager ensure the team is fully productive?
Show answerHide answer

Correct answer: D Work with the product owner to ensure the project backlog is prioritized.

Question 402 Choose 1
Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?
Show answerHide answer

Correct answer: B Establish a pull communications method to access knowledge repositories and lessons learned.

Question 403 Choose 1
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.

How can the project manager strategize the use of a hybrid approach to the organization?
Show answerHide answer

Correct answer: A Present the benefits of a hybrid approach to key stakeholders to get their support.

Question 404 Choose 1
A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?
Show answerHide answer

Correct answer: B Schedule a meeting with the stakeholder to better understand their request

Question 405 Choose 1
A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses predictive approaches, does not like virtual tools such as chats, task trackers, and so forth.

They prefer email, telephone calls, and face-to-face meetings.

How should the project manager approach this situation?
Show answerHide answer

Correct answer: B Align and agree with the stakeholder on the communication approach.

Question 406 Choose 1
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?
Show answerHide answer

Correct answer: B Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.

Question 407 Choose 1
A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?
Show answerHide answer

Correct answer: D Newspapers

Question 408 Choose 1
After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?
Show answerHide answer

Correct answer: D Check the stakeholder register and ensure that every stakeholder's information is correct and current.

Question 409 Choose 1
A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the deployment.

What should the project manager have done to prevent the delay?
Show answerHide answer

Correct answer: A Obtained all critical information ahead of time

Question 410 Choose 1
A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?
Show answerHide answer

Correct answer: C Perform trend analysis.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt