During daily team standup meetings, team members constantly ask about which tasks they
should focus on first. How should the project
manager ensure the team is fully productive?
Show answerHide answer
Correct answer: DWork with the product owner to ensure the project backlog is prioritized.
Question 402Choose 1
Knowledge sharing has been a key priority for a complex technological project with a large
number of team members. During the project
execution phase, the project manager receives numerous complaints from all team
members that they are overloaded with knowledge-sharing
emails, which contain useful information but are unmanageable due to the high volume.
What should the project manager do to solve this problem?
Show answerHide answer
Correct answer: BEstablish a pull communications method to access knowledge repositories and lessons
learned.
Question 403Choose 1
A company is about to start a complex research project. Due to the level of uncertainty, the
project manager recommends the use of a hybrid approach; however, the organization only
has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
Show answerHide answer
Correct answer: APresent the benefits of a hybrid approach to key stakeholders to get their support.
Question 404Choose 1
A project manager joins an existing project. One project stakeholder is unhappy with the
frequency and types of project updates received and has made a request for more What
should the project manager do next?
Show answerHide answer
Correct answer: BSchedule a meeting with the stakeholder to better understand their request
Question 405Choose 1
A project manager is working on a financial system implementation project for a
government company. One of the key stakeholders, who uses
predictive approaches, does not like virtual tools such as chats, task trackers, and so forth.
They prefer email, telephone calls, and face-to-face
meetings.
How should the project manager approach this situation?
Show answerHide answer
Correct answer: BAlign and agree with the stakeholder on the communication approach.
Question 406Choose 1
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the
project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a meeting with the project team and the key stakeholder as soon as possible
to discuss and agree on an approach.
Question 407Choose 1
A project being constructed in a remote rural area is nearing the end of construction. The
project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?
Show answerHide answer
Correct answer: DNewspapers
Question 408Choose 1
After the demo on a software project, one of the key stakeholders contacted the scrum
master and complained that they were unaware of changes made to the project. After
checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.
What should the scrum master do?
Show answerHide answer
Correct answer: DCheck the stakeholder register and ensure that every stakeholder's information is
correct and current.
Question 409Choose 1
A team working on a close deployment waits to receive critical information from the
customer. The customer keeps postponing sending the information which is delaying the
deployment.
What should the project manager have done to prevent the delay?
Show answerHide answer
Correct answer: AObtained all critical information ahead of time
Question 410Choose 1
A project manager is leading a software development project that will assist in maintenance
management for a power plant. The project manager is analyzing project performance data
and trying to forecast if the project will have any slippage in the future.
What should the protect manager do?
Show answerHide answer
Correct answer: CPerform trend analysis.