After conducting a performance assessment, the project manager identified that some gaps
still exist. What should the project manager ensure?
Show answerHide answer
Correct answer: BPerformance improvement programs are organized for all team members who were
assessed.
Question 392Choose 1
A project manager is managing an agile project for the first time. Early on, the project
manager discovers the team is struggling to agree on the scope of a feature during a sprint.
How should the project manager help the team resolve the issue?
Show answerHide answer
Correct answer: DEncourage the team to collaborate to resolve their understanding of the feature.
Question 393Choose 1
A project manager is leading a strategic and competitive advantage project for a healthcare
organization that is in its testing phase. The team has
been working on this project for 6 months, and the morale of the team is low due to the
schedule.
What can the project manager do to motivate the team?
Show answerHide answer
Correct answer: CSpeak with the project management office (PMO) and request a 2-week extension of the
schedule so the team can have rotational time off.
Question 394Choose 1
A team has been working for some time on a project with incremental deliveries. The
project manager noticed that one of the team members is less engaged in team meetings,
yet delivers promptly. While discussing the source of demotivation, the team member
informed the project manager that this is due to a feeling of lack of skills in dealing with new
tasks.
How should the project manager address the issue?
Show answerHide answer
Correct answer: DDiscuss growth and development needs with the team member and provide learning
opportunities accordingly.
Question 395Choose 1
A typically high-performing team member has started to demonstrate a performance drop
as well as some aggressive behaviors toward other team members in meetings.
The project manager has worked with this individual for many months on this project and
has not seen this type of behavior before.
What should the project manager do?
Show answerHide answer
Correct answer: ADiscuss the project manager's observations with the individual to determine why they
are behaving this way.
Question 396Choose 1
A team has individual daily start times for each team member. Sometimes the overlap
between team member working hours is short. During those
times, the interactions and work as a team are reduced and ineffective.
What should the project manager do?
Show answerHide answer
Correct answer: CAsk the team to define a team charter and agree on core working hours.
Question 397Choose 1
During the testing phase of a project, the project manager is made aware that components
delivered from a specific vendor have defects. However, the vendor refuses to fix the
defects because it will incur additional costs for them.
What should the project manager do next?
Show answerHide answer
Correct answer: BReview the acceptance criteria defined with the vendor.
Question 398Choose 3
A project manager is assigned to a time-bound internal project on quality improvement.
During project execution, the project manager observes that a specific team member is
being isolated
by other team members.
Which three actions should the project manager take? (Choose three)
Show answerHide answer
Correct answer: A, C, EArrange and conduct team-building sessions to improve team effectiveness.Get feedback from other team members to understand what led to this situation.Obtain feedback from the isolated team member to understand the situation.
Question 399Choose 1
A project manager just completed a successful deployment and is preparing to transition
the project to an operational state before starting closeout actions. What should the project
manager do to ensure that the project is ready to move to an operational state?
Show answerHide answer
Correct answer: AMeet with the project team to review the work breakdown structure (WBS) and confirm
deliverables have been delivered.
Question 400Choose 1
An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to
the volatility of cryptocurrency, both parties have
agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration
and halt the project when the agreed price is reached.
Which approach should be used in this situation?
Show answerHide answer
Correct answer: DAn incremental approach with a minimum viable product (MVP).