PMI certification · Exam PMP

PMP Mock Exam Page 40

Project Management Professional (PMP) July 2026 Update

Free PMP mock exam questions 391–400, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Free PMP questions

391–400 of 636 free
Question 391 Choose 1
After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?
Show answerHide answer

Correct answer: B Performance improvement programs are organized for all team members who were assessed.

Question 392 Choose 1
A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?
Show answerHide answer

Correct answer: D Encourage the team to collaborate to resolve their understanding of the feature.

Question 393 Choose 1
A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?
Show answerHide answer

Correct answer: C Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.

Question 394 Choose 1
A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.

How should the project manager address the issue?
Show answerHide answer

Correct answer: D Discuss growth and development needs with the team member and provide learning opportunities accordingly.

Question 395 Choose 1
A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.

The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.

What should the project manager do?
Show answerHide answer

Correct answer: A Discuss the project manager's observations with the individual to determine why they are behaving this way.

Question 396 Choose 1
A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those times, the interactions and work as a team are reduced and ineffective.

What should the project manager do?
Show answerHide answer

Correct answer: C Ask the team to define a team charter and agree on core working hours.

Question 397 Choose 1
During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.

What should the project manager do next?
Show answerHide answer

Correct answer: B Review the acceptance criteria defined with the vendor.

Question 398 Choose 3
A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated by other team members.

Which three actions should the project manager take? (Choose three)
Show answerHide answer

Correct answer: A, C, E Arrange and conduct team-building sessions to improve team effectiveness.Get feedback from other team members to understand what led to this situation.Obtain feedback from the isolated team member to understand the situation.

Question 399 Choose 1
A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?
Show answerHide answer

Correct answer: A Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.

Question 400 Choose 1
An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.

Which approach should be used in this situation?
Show answerHide answer

Correct answer: D An incremental approach with a minimum viable product (MVP).

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt