A project sponsor has approved the project charter and business case. The project
manager has reviewed the artifacts to initiate the project and is unclear if the intended
benefits of the project align with the strategic objectives of the business.
What should the project manager do first?
Show answerHide answer
Correct answer: BMeet with the project sponsor to better understand the strategic benefits of the project.
Question 382Choose 1
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The
burndown chart is shown below. What should the team do next?
Show answerHide answer
Correct answer: DContinue with the sprint work as planned and keep monitoring.
Question 383Choose 1
A new team member joins an agile team. In a previous role, this team member was a
subject matter expert (SME). This team member often directs the team on how to solve
problems based on previous experience.
What should the project manager do first?
Show answerHide answer
Correct answer: DLet the new team member know that even if they know the answer, it is better to give the
team a chance to solve their own problems
In the daily check-in meeting, a team member informs the project team that the licenses for
one of the components that will be used will expire in
a couple of months. The licensing cost is significant.
What should the project manager do next?
Show answerHide answer
Correct answer: AEvaluate the impact of nonrenewal of the license.
Question 385Choose 1
A project manager is tasked with developing a coaching model to support and recognize
team members' growth.
What should the project manager consider when defining their coaching strategy?
Show answerHide answer
Correct answer: CIndividual and personal objectives
Question 386Choose 1
A project manager was replaced in the early phases of a new project. The new project
manager discovers that the business team is not supporting the project. After
discussing these concerns with the team, it is determined that the project does not have the
full support of senior management.
What should the new project manager do next?
Show answerHide answer
Correct answer: CStudy the stakeholder analysis to understand which stakeholder holds the most
influence and seek their assistance.
Question 387Choose 1
A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The
project manager is working on a predictive project and thinks this request will distract the
team and delay the project.
What should the project manager do first?
Show answerHide answer
Correct answer: AAssess and analyze the impact of using these metrics.
Question 388Choose 1
A project team member, who is inexperienced in system development work is not
performing well. Currently, there are no other staff members
available who are qualified to complete the work.
What should the project manager do?
Show answerHide answer
Correct answer: AAssess the team member's development requirements and arrange for the team
member to receive training.
Question 389Choose 1
A project stakeholder complained that they did not receive an important delivery that was
stated in the schedule. The team member responsible for this deliverable explained that
they sent an email to the stakeholder, advising them that the deliverable would not be
delivered on time.
What should the project manager have done to avoid this situation?
Show answerHide answer
Correct answer: DCommunicated with the stakeholder directly regarding the delivery delay.
Question 390Choose 1
A healthcare company is in the process of deploying an innovative healthcare solution
globally. The project team has completed a limited release.
The stakeholders have raised concerns about global healthcare guidelines and risks.
What should the project manager do next?
Show answerHide answer
Correct answer: CReview compliance and regulatory requirements with stakeholders.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.