Question 381 Choose 1
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?
Show answerHide answer

Correct answer: B Meet with the project sponsor to better understand the strategic benefits of the project.

Question 382 Choose 1
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
Show answerHide answer

Correct answer: D Continue with the sprint work as planned and keep monitoring.

Question 383 Choose 1
A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?
Show answerHide answer

Correct answer: D Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Question 384 Choose 1
In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant.

What should the project manager do next?
Show answerHide answer

Correct answer: A Evaluate the impact of nonrenewal of the license.

Question 385 Choose 1
A project manager is tasked with developing a coaching model to support and recognize team members' growth.

What should the project manager consider when defining their coaching strategy?
Show answerHide answer

Correct answer: C Individual and personal objectives

Question 386 Choose 1
A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After discussing these concerns with the team, it is determined that the project does not have the full support of senior management.

What should the new project manager do next?
Show answerHide answer

Correct answer: C Study the stakeholder analysis to understand which stakeholder holds the most influence and seek their assistance.

Question 387 Choose 1
A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.

What should the project manager do first?
Show answerHide answer

Correct answer: A Assess and analyze the impact of using these metrics.

Question 388 Choose 1
A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members available who are qualified to complete the work.

What should the project manager do?
Show answerHide answer

Correct answer: A Assess the team member's development requirements and arrange for the team member to receive training.

Question 389 Choose 1
A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder, advising them that the deliverable would not be delivered on time.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: D Communicated with the stakeholder directly regarding the delivery delay.

Question 390 Choose 1
A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release.

The stakeholders have raised concerns about global healthcare guidelines and risks.

What should the project manager do next?
Show answerHide answer

Correct answer: C Review compliance and regulatory requirements with stakeholders.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt