Question 371 Choose 1
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?
Show answerHide answer

Correct answer: C Check the organizational process assets (OPAs).

Question 372 Choose 1
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?
Show answerHide answer

Correct answer: A Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

Question 373 Choose 1
A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?
Show answerHide answer

Correct answer: D Perform an impact analysis to see the effect on the project.

Question 374 Choose 1
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?
Show answerHide answer

Correct answer: A Personas

Question 375 Choose 1
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?
Show answerHide answer

Correct answer: B Review the new requirements with the compliance department to determine if a change request is needed.

Question 376 Choose 1
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?
Show answerHide answer

Correct answer: D Review this stakeholder's communication requirements.

Question 377 Choose 1
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?
Show answerHide answer

Correct answer: D A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Question 378 Choose 1
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?
Show answerHide answer

Correct answer: D Develop and define a communication strategy for stakeholders.

Question 379 Choose 1
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?
Show answerHide answer

Correct answer: C Comply with the regulatory requirements and work to compress the project schedule.

Question 380 Choose 1
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?
Show answerHide answer

Correct answer: B Keep the focus on the priority items while the change goes through the change control process.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.