A project manager is newly assigned to the second phase of an ongoing project. During the
implementation, a defect occurred and no one knows how to fix it, as the former
engineering team has moved to another project. The customer warns that previously, this
defect negatively affected the project schedule.
What should the project manager do first?
Show answerHide answer
Correct answer: CCheck the organizational process assets (OPAs).
Question 372Choose 1
A project manager has been managing an agile project for 6 months. Over the last two
iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the
expected velocity?
Show answerHide answer
Correct answer: AUse retrospectives to better understand the new technology's impact on the schedule,
map the skill gaps, and adjust the team accordingly.
Question 373Choose 1
A project manager is in the middle of handling a major upgrade to an existing product. The
project manager learns that the resources initially promised as part of the project are being
moved to another priority project.
What should the project manager do?
Show answerHide answer
Correct answer: DPerform an impact analysis to see the effect on the project.
Question 374Choose 1
A project team is executing a large regulatory project comprised of a multitude of internal
and external stakeholders. An initial impact analysis revealed several systems, including an
enhancement to existing modules as well as new builds. After completion of the initial
design workshop, the team conducted a brainstorming session to better understand the
types of likely users.
Which technique will best serve this purpose?
Show answerHide answer
Correct answer: APersonas
Question 375Choose 1
A multimillion-dollar project has started and is in the execution phase. A local regulatory
authority has just announced changes to the requirements that will need to be implemented
in 6 months, prior to completing the project execution phase.
What should the project manager do next?
Show answerHide answer
Correct answer: BReview the new requirements with the compliance department to determine if a change
request is needed.
Question 376Choose 1
A project team member informs the project manager that a stakeholder is contacting the
team member to request status updates. The team member is being distracted by these
repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
Show answerHide answer
Correct answer: DReview this stakeholder's communication requirements.
Question 377Choose 1
A project manager is working with a customer's team on a new project. Some product
definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a
specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
Show answerHide answer
Correct answer: DA hybrid approach will allow for management of the requirement uncertainties as well as
the date restriction.
Question 378Choose 1
A project manager is assigned to a new project team that has several stakeholders who
can have significant influence over the project outcomes.
The project manager categorized the stakeholders into four different groups and wants to
define the communication strategy.
How should the project manager handle communication?
Show answerHide answer
Correct answer: DDevelop and define a communication strategy for stakeholders.
Question 379Choose 1
A company initiated a project to introduce a new product to the market. The product must
undergo the industry's regulatory process prior to approval and launch However, the
company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
Show answerHide answer
Correct answer: CComply with the regulatory requirements and work to compress the project schedule.
Question 380Choose 1
A project interfaces with other projects that are in the same portfolio but are being
developed in international locations. One of the international projects has suggested a
tactical change that needs to be implemented in this project.
What should the project manager do next ?
Show answerHide answer
Correct answer: BKeep the focus on the priority items while the change goes through the change control
process.