A company is undergoing a digital transformation and is changing its project portfolio to an
agile approach. As a result, the leadership is looking to update the performance measuring
system for the workforce.
What should the project manager propose?
Show answerHide answer
Correct answer: BPropose an approach based on value measurement, such as the use of objectives and
key results.
Question 362Choose 1
During a team meeting, the new agile project manager becomes aware that there are many
complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees
who confirmed that the project was stable.
How should the new project manager address these concerns?
Show answerHide answer
Correct answer: CHold a brainstorming session to identify the root cause of the complaints.
Question 363Choose 2
A project manager is managing an internal project with a tight budget and schedule. While
executing the project, the project manager realizes that
some stakeholders are working against the success targets of the project.
What should the project manager do to ensure successful project delivery? (Choose two)
Show answerHide answer
Correct answer: A, EUpdate the project stakeholder analysis and methods to satisfy the stakeholders’
requirements.Engage all stakeholders in the project including the unsupportive stakeholders.
Question 364Choose 1
A project manager implementing a hybrid project is dealing with multiple stakeholders in a
rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
Show answerHide answer
Correct answer: DUse iterative life cycles involving stakeholders to enable the team to improve the product
end result through successive prototypes.
Question 365Choose 1
A project manager was recently assigned to a project that is in the execution phase and is
experiencing roadblocks. During a review of the
processes and procedures, the project manager notices similarities to a previous project
that experienced similar roadblocks. The project manager
reviews the task schedule and finds that certain tasks are well behind expectations. In
speaking with the project team, the project manager
confirms that the team is following the processes exactly.
What should the project manager do?
Show answerHide answer
Correct answer: CReview and amend the processes to ensure only value-adding activities are present.
Question 366Choose 1
A project manager is assigned to an organizational transformation project. The company
typically defines individual performance plans at the beginning of the year, and functional
managers conduct feedback reviews at the end of the year. The transformation project
team members are concerned that the work they are doing for this project is not aligned
with the work included in their individual performance plan for the year.
What should the project manager do?
Show answerHide answer
Correct answer: AMeet with the functional managers to align the expected frequency and results reporting
for the team members.
Question 367Choose 1
A project manage is in the middle of an angle project comprised of 100 user stories broken
down into five iterations. Each user story is worth U$$50. The actual expenditure is
U$$2,00 and 50 user stories have been delivered.
Which statement is true?
Show answerHide answer
Correct answer: BThe project is under budget and on schedule.
Question 368Choose 1
A project team was hired to perform on-site duties, but there were unexpected
circumstances that required the entire team to work remotely Some team members
returned to their hometowns and they are now requesting reimbursement for operational
expenditures
What should the project manager do?
Show answerHide answer
Correct answer: AFollow the Perform integrated Change Control process and submit a change request
Question 369Choose 1
During the last two iterations of a project, one of the team members had low performance.
The project manager conducted two feedback sessions with the team member and
escalated the issue to the resource manager and project sponsor, but there has been no
improvement.
What should the project manager do next?
Show answerHide answer
Correct answer: CRequest a new resource to execute the activities.
Question 370Choose 1
A company is running a project to eliminate a sales channel that has been unprofitable for
the past 3 years. A key stakeholder from another area, who has legacy ties to that sales
channel, objects to the project.
What should the project manager do in this situation?
Show answerHide answer
Correct answer: AAssess the impact of the stakeholder and engage properly.