Question 361 Choose 1
A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?
Show answerHide answer

Correct answer: B Propose an approach based on value measurement, such as the use of objectives and key results.

Question 362 Choose 1
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?
Show answerHide answer

Correct answer: C Hold a brainstorming session to identify the root cause of the complaints.

Question 363 Choose 2
A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)
Show answerHide answer

Correct answer: A, E Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.Engage all stakeholders in the project including the unsupportive stakeholders.

Question 364 Choose 1
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?
Show answerHide answer

Correct answer: D Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Question 365 Choose 1
A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.

What should the project manager do?
Show answerHide answer

Correct answer: C Review and amend the processes to ensure only value-adding activities are present.

Question 366 Choose 1
A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?
Show answerHide answer

Correct answer: A Meet with the functional managers to align the expected frequency and results reporting for the team members.

Question 367 Choose 1
A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?
Show answerHide answer

Correct answer: B The project is under budget and on schedule.

Question 368 Choose 1
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?
Show answerHide answer

Correct answer: A Follow the Perform integrated Change Control process and submit a change request

Question 369 Choose 1
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?
Show answerHide answer

Correct answer: C Request a new resource to execute the activities.

Question 370 Choose 1
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?
Show answerHide answer

Correct answer: A Assess the impact of the stakeholder and engage properly.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt