A project manager is assigned to a project that is in the execution phase that has different
types of stakeholders. Some of the stakeholders are very interested in the project, whereas
other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
Show answerHide answer
Correct answer: ALook at the stakeholder assessment matrix to find stakeholders' interests and make
updates if necessary.
Question 352Choose 1
In a marine construction project, the project manager is informed by the marine authority
that the work permit will not be issued until certain environmental reinforcement work has
been completed. After reviewing the project management plan, the reinforcement work is
not included in the project scope.
What should the project manager do?
Show answerHide answer
Correct answer: CStart the organization's change control process via a change request.
Question 353Choose 1
During execution of an agile project, a project manager realizes the budget is almost
completely used, but the project is not close to being completed. What should the project
manager do to address this concern?
Show answerHide answer
Correct answer: CReview the backlog and find opportunities to reprioritize the work and reduce the project
scope
Question 354Choose 1
A project manager is assigned to a project team midway through execution. Several
dependencies are impacting the project, and the project manager feels the team is not
adequately informed of the impacting changes.
What should the project manager do first?
Show answerHide answer
Correct answer: CConsult the communications management plan.
Question 355Choose 1
An organization initiated a project in a complex program. The project lead notices that the
team is demotivated because the current project framework implemented by the project
management office (PMO) is not compatible with agile delivery
What should the project lead do?
Show answerHide answer
Correct answer: BAsk the PMO to review the framework
Question 356Choose 1
A project manager is reviewing the lessons learned for an historical project. The review
identifies that the client's engineer was adamant that they review all changes, even those
not identified in the contract.
How should the project manager deal with this when planning the project?
Show answerHide answer
Correct answer: AEnsure the change management plan highlights this requirement to prevent future
issues.
Question 357Choose 1
A project manager for a technologically complex engagement reviews the key project
indicators with the main stakeholders on a regular basis. During one of the meetings,
the project sponsor explains that they are using the project manager's risk register as a
way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk
register?
Show answerHide answer
Correct answer: AReview the risks throughout project execution.
Question 358Choose 1
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific
resources to all of the project tasks.
What should the project manager do?
Show answerHide answer
Correct answer: BAssign the unallocated tasks to the functional role and then reallocate when the
resources are available.
Question 359Choose 1
A CEO of a general contracting company urgently asks the project manager to sign up two
project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above
their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
Show answerHide answer
Correct answer: CObserved and assessed the competencies and skills of the team members and
analyzed the training material beforehand
Question 360Choose 1
A team member has very strong technical skills and is interested in a leadership role. A
leadership position opens up outside of the team in the organization. The project manager
has observed that the team member has a major gap in communicating in a professional
manner.
What should the project manager do?
Show answerHide answer
Correct answer: BRecommend the team member for effective communication training and support their
career development interests.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.