Question 341
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
Show answerHide answer

Explanation

Question 342 Choose 1
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?
Show answerHide answer

Correct answer: C At the end of each and every iteration

Question 343 Choose 1
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
Show answerHide answer

Correct answer: B Foster an environment of open communication where all parties can discuss issues and agree on objectives.

Question 344 Choose 1
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?
Show answerHide answer

Correct answer: C Make documentation a standard part of the definition of done (DoD).

Question 345 Choose 1
A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became concerned that the product quality will be sacrificed.

What should the project manager do?
Show answerHide answer

Correct answer: C Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

Question 346 Choose 1
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?
Show answerHide answer

Correct answer: B Used bottom-up estimating

Question 347 Choose 1
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
Show answerHide answer

Correct answer: C Promote, inspire, and follow the stakeholder engagement process.

Question 348 Choose 1
A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?
Show answerHide answer

Correct answer: D Include compliance within the development tools.

Question 349 Choose 1
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
Show answerHide answer

Correct answer: B Coach the project owner about the implications of unplanned meetings.

Question 350 Choose 1
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
Show answerHide answer

Correct answer: C Analyze the stakeholders.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.