A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?
Show answerHide answer

Correct answer: D Assess the influence and power of the employee to see if the employee will add value.

Question 332 Choose 1
Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to ensure the project is delivered successfully?
Show answerHide answer

Correct answer: B Invite the vendor to a meeting to discuss the concerns.

Question 333 Choose 1
A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?
Show answerHide answer

Correct answer: A Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

Question 334 Choose 1
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?
Show answerHide answer

Correct answer: C Understand what the team member wants and find possible opportunities to address it.

Question 335 Choose 1
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?
Show answerHide answer

Correct answer: D Program managers

Question 336 Choose 1
A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?
Show answerHide answer

Correct answer: C The product owner has evaluated the product against the definition of done (DoD).

Question 337 Choose 1
A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?
Show answerHide answer

Correct answer: C Assist the team in defining a minimum viable product (MVP) by the launch date.

Question 338 Choose 1
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?
Show answerHide answer

Correct answer: D Make changes to reprioritize the backlog because of the obstacle.

Question 339 Choose 1
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?
Show answerHide answer

Correct answer: D Reassess continually to remove blockers for the team.

Question 340 Choose 1
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?
Show answerHide answer

Correct answer: C Communicate the project's impact and plans to engage the project team throughout the project.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt