A senior employee with experience relevant to a highly complex project is seeking a
promotion to be able to join the project. The employee has made a recommendation
regarding the project. The project charter was recently approved.
How should the project manager address the employee's request?
Show answerHide answer
Correct answer: DAssess the influence and power of the employee to see if the employee will add value.
Question 332Choose 1
Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to
ensure the project is delivered successfully?
Show answerHide answer
Correct answer: BInvite the vendor to a meeting to discuss the concerns.
Question 333Choose 1
A project team member was unhappy with a new change in project governance and
complained to one of the project sponsors. The project sponsor challenged the project
manager.
How should the project manager resolve this conflict?
Show answerHide answer
Correct answer: AArrange a meeting with the project team member and project sponsor to discuss the
change and obtain consensus.
Question 334Choose 1
A project manager is leading a project that has been in execution for 1 year. An
experienced team member is performing well, but often disagrees with the project manager
and refuses to implement their decisions. Part of the team supports the team member's
defiance, while the other team members do not.
What should the project manager do?
Show answerHide answer
Correct answer: CUnderstand what the team member wants and find possible opportunities to address it.
Question 335Choose 1
A project manager is leading a cross-organizational project that is replacing a platform on
which various solutions used by 15 business units were built. The project is part of a large
program of work, and some of the resources are shared with other projects outside of the
program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage
interdependencies?
Show answerHide answer
Correct answer: DProgram managers
Question 336Choose 1
A product owner is invited to a sprint review meeting. At the end of the review, the product
owner says that the increment is ready to be delivered to the customer.
What conclusion should the project manager come to with regard to the product owner's
statement?
Show answerHide answer
Correct answer: CThe product owner has evaluated the product against the definition of done (DoD).
Question 337Choose 1
A company wants to be a pioneer in its industry and has announced the launch date of a
new innovative product. After the first sprint planning, the
team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?
Show answerHide answer
Correct answer: CAssist the team in defining a minimum viable product (MVP) by the launch date.
Question 338Choose 1
A team is using an agile approach to maintain the project backlog. A new project obstacle
was identified as a blocker and added to the backlog list. The team is facing challenges to
remove this obstacle
What should the project manager do next?
Show answerHide answer
Correct answer: DMake changes to reprioritize the backlog because of the obstacle.
Question 339Choose 1
Due to unforeseen circumstances, a contractor was unable to mobilize the project team,
which was necessary to conduct face-to-face meetings and discussions. Virtual meetings
were subsequently put in place, but the local project team and end users now face a
communication gap that is causing the team's low performance.
What should the project manager do?
Show answerHide answer
Correct answer: DReassess continually to remove blockers for the team.
Question 340Choose 1
A company has decided to initiate a project to eliminate a sales channel that has been
unprofitable for the past 3 years. Some members of the project team are pessimistic about
the project.
What should the project manager do in this situation?
Show answerHide answer
Correct answer: CCommunicate the project's impact and plans to engage the project team throughout the
project.