Question 321 Choose 1
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?
Show answerHide answer

Correct answer: B Risk occurred

Question 322 Choose 1
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development.

Which action should the project manager take to resolve the quality issues?
Show answerHide answer

Correct answer: A Plan for continuous validation of the product.

Question 323 Choose 1
A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?
Show answerHide answer

Correct answer: C Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

Question 324 Choose 1
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?
Show answerHide answer

Correct answer: C Schedule regular project audits.

Question 325 Choose 2
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)
Show answerHide answer

Correct answer: C, E Analyze the business benefits criteria and assumptionsSchedule a project review meeting to analyze the root cause

Question 326 Choose 1
A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?
Show answerHide answer

Correct answer: B Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

Question 327 Choose 1
A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?
Show answerHide answer

Correct answer: D Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Question 328 Choose 1
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?
Show answerHide answer

Correct answer: D Request that the project team develop a release plan and roadmap for the project.

Question 329 Choose 1
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?
Show answerHide answer

Correct answer: D Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Question 330 Choose 1
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?
Show answerHide answer

Correct answer: D Set expectations for contributions ahead of the meeting

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt