A software delivery project began having technical impediments. The issue may cause a
delay of the deliverables. The technical service team has been working on the issue, but
the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
Show answerHide answer
Correct answer: CUpdate the issue log with the status and priority.
Question 312Choose 2
A key project stakeholder has started to escalate all issues and main requirements to the
project sponsor. The project manager is concemed about the team not receiving direct
communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the
stakeholder? (Choose two)
Show answerHide answer
Correct answer: A, DSchedule regular meetings with the key stakeholder to provide updates and receive
feedback,Promote an adaptive and transparent environment where the team can easily
communicate with the stakeholders.
Question 313Choose 1
A project manager is managing a very important business transformation project. The goal
of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
Show answerHide answer
Correct answer: DIncremental delivery, to ensure that mobile capability is released fast to the users
Question 314Choose 1
A prefeasibility study for a new renewable energy project is nearing approval. To ensure
that the project time lines are maintained, activities associated with the feasibility study
must continue while the prefeasibility study is being approved.
How should the project manager proceed?
Show answerHide answer
Correct answer: CObtain approval to proceed with the feasibility study as a parallel activity while the
prefeasibility study is approved
Question 315Choose 1
A project manager is managing a new development program to automate some technical
functions. During project kickoff, the project manager
expresses the need for a technical architect to support the project for a moderate amount
of time. The project sponsor informs the project
manager about an existing technical architect who possesses valuable knowledge but is
already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to
ensure project success?
Show answerHide answer
Correct answer: BShare the existing technical architect so they can be allocated to the current project and
other projects.
Question 316Choose 1
An organization is transitioning to agile. The project manager is discussing how to manage
risks with the development team in light of the transition for a particular project.
The team estimates the risk level as low.
What should the project manager do?
Show answerHide answer
Correct answer: BCreate a risk register to identify, capture, review, and manage risks using a risk
management process.
Question 317Choose 2
A project team member raised a risk that the threat of country-wide power cuts may affect
the project time line for a software development project. In the last month, this risk
materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two)
Show answerHide answer
Correct answer: B, DAnalyze the impact of the issue and submit a change request to update the project
schedule.Extend the project deadline and update the project schedule to reflect the delay.
Question 318Choose 1
An iteration is almost finished, but the team is struggling to complete the stories that require
more time. What should the project manager do first?
Show answerHide answer
Correct answer: AMeet with the project team to develop a proper resolution to the issue.
Question 319Choose 1
A project manager is leading a project that will be delivered using a Scrum framework. The
organization has an innovative project management office (PMO) that fully supports agile
and also has a very friendly procurement team. A new vendor needs to be engaged to
provide more developers for a new reporting platform.
What should the project manager do?
Show answerHide answer
Correct answer: DUse a formal approach using procurement policies, procedures, forms, and work
instructions.
Question 320Choose 1
A project manager who is experienced in predictive and adaptive approaches has been
assigned to a new project. Most of the project
stakeholders have only worked on predictive projects, and only a few have been exposed
to adaptive projects.
What should the project manager do?
Show answerHide answer
Correct answer: DUnderstand the scope complexity and project magnitude prior to determining which
approach to use.