Question 311 Choose 1
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?
Show answerHide answer

Correct answer: C Update the issue log with the status and priority.

Question 312 Choose 2
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
Show answerHide answer

Correct answer: A, D Schedule regular meetings with the key stakeholder to provide updates and receive feedback,Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

Question 313 Choose 1
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?
Show answerHide answer

Correct answer: D Incremental delivery, to ensure that mobile capability is released fast to the users

Question 314 Choose 1
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?
Show answerHide answer

Correct answer: C Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

Question 315 Choose 1
A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?
Show answerHide answer

Correct answer: B Share the existing technical architect so they can be allocated to the current project and other projects.

Question 316 Choose 1
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?
Show answerHide answer

Correct answer: B Create a risk register to identify, capture, review, and manage risks using a risk management process.

Question 317 Choose 2
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)
Show answerHide answer

Correct answer: B, D Analyze the impact of the issue and submit a change request to update the project schedule.Extend the project deadline and update the project schedule to reflect the delay.

Question 318 Choose 1
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
Show answerHide answer

Correct answer: A Meet with the project team to develop a proper resolution to the issue.

Question 319 Choose 1
A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?
Show answerHide answer

Correct answer: D Use a formal approach using procurement policies, procedures, forms, and work instructions.

Question 320 Choose 1
A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?
Show answerHide answer

Correct answer: D Understand the scope complexity and project magnitude prior to determining which approach to use.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt