A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager
calls a team meeting to discuss the requirements, and the team learns that the design
changes can be made at no additional cost.
What should the project manager direct the team to do?
Show answerHide answer
Correct answer: DRequest a change through the change control process to manage the new
cybersecurityrequirements.
Question 302Choose 1
During the execution of a project, a company decides that everybody will need to take
vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?
Show answerHide answer
Correct answer: CAgree with functional management and team members on a vacation schedule that
would minimally impact the project schedule.
Question 303Choose 1
As a result of the first iteration review, the stakeholders' feedback indicated that they saw
more technical features than business ones What should the project manager do?
Show answerHide answer
Correct answer: BReview this topic with the product owner before the next iteration planning
A project has come to the closing stage. The work is generally finished, and the project
manager wants to commence the closure process for the project. What should the project
manager ensure is in place prior to the closing process?
Show answerHide answer
Correct answer: BThe contractual deliverables of the project have been accepted.
Question 305Choose 1
The project manager of a high-risk project is concerned about a delay in the schedule that
might force the project to ‘move its go-live date. What should the project manager do next?
Show answerHide answer
Correct answer: CCapture the risk in the risk register and monitor it to prevent it from becoming an issue
by taking the proper response action.
Question 306Choose 1
A project manager has been assigned to an important project that will help set the future of
the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project
manager follow this process as well. However, the functional manager has expressed
concerns about the use of new tools on such an important project.
What should the project manager do?
Show answerHide answer
Correct answer: CMake the decision on which project approach to use that would best fit the project.
Question 307Choose 1
An organization is transitioning to an agile approach. At the project's first sprint review, the
product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
Show answerHide answer
Correct answer: AOrganize a sprint retrospective and discuss the issues and how they can be avoided in
the next sprint.
Question 308Choose 1
A project manager has established daily standup meetings with the team during the
execution phase of the project. The project manager has been successful in removing 75%
of the
obstacles reported, but the timeline continues to deviate further each day with no signs of
improvement.
What should the project manager have done to avoid this issue?
Show answerHide answer
Correct answer: APrioritized blockers on the critical path
Question 309Choose 1
A project manager is working in a company that has several global offices. During resource
planning for a new project, the project manager realizes that the company requires projects
to include team members from different continents.
What should the project manager do to ensure a successful project execution?
Show answerHide answer
Correct answer: CConnect with every location and check their preferred methods of communication.
Question 310Choose 1
A project manager has been assigned to a new digital product line, which the company
hopes will boost their revenue. The product is complex and requires customer feedback to
continually refine the product. The project is being handled by a cross-functional agile
team.
What should the project manager do to ensure value is delivered quickly?
Show answerHide answer
Correct answer: APlan the project to deliver value incrementally with regular releases.