A project manager is managing an internal software development project that is on
schedule to complete in 1 month. The project should begin seeing value once the system is
online,
yet some stakeholders lack an understanding of how it will provide value to the
organization.
What should the project manager do next?
Show answerHide answer
Correct answer: CCoordinate with the stakeholders to ensure the benefits management plan is in
alignment with the goals.
Question 292Choose 1
A project manager has been assigned to an emergency project that must be completed
within the next few weeks. The project manager realizes this will have an impact on the
local community. As the work is near a school, the project manager has engaged with them
to understand their needs
How should the project manager ensure the work continues smoothly?
Show answerHide answer
Correct answer: DLiaise with the school to include nonworking project hours during school start and finish
times
Question 293Choose 1
Anew systems project requires feedback from the accounting manager at the beginning of
solution discussions and before meeting with other functional managers. The project
manager knows the accounting manager will not be available until a few days before the
deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
Show answerHide answer
Correct answer: DBegin discussions with other functional managers and meet with the accounting
manager later.
Question 294Choose 1
A project manager is managing a hybrid project that is using a contractor for a few key
deliverables. The contractor has been hired to perform an important delivery, but has not
yet confirmed that they can meet the required schedule.
What should the project manager do?
Show answerHide answer
Correct answer: CPlan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,
Question 295Choose 1
Many issues have been encountered in a project due to the low competence of the team
members. These issues might lead to poor project performance and potentially to project
termination.
What should the project manager do?
Show answerHide answer
Correct answer: CInvest in coaching and training for all project team members.
Question 296Choose 1
During project execution for an innovative product, a project team has been working hard to
meet the deadlines. However, one of the team members will be leaving in 3 weeks and will
be replaced with a new team member.
How should the team share tacit knowledge?
Show answerHide answer
Correct answer: BHave the team meet on a regular basis and share their experiences, challenges, and
lessons learned.
Question 297Choose 1
A project manager for a digital transformation project has already received the business
needs for the project. When gathering requirements, the project manager discovers that not
all of the requirements can be delivered with the available resources, but that some of the
requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
Show answerHide answer
Correct answer: BGather all stakeholders and provide recommendations on a smaller, more feasible
project scope,
Question 298Choose 1
A project manager Is leading an agile software development project with strict deadlines
The client complained that the last deployment did not meet the acceptance criteria The
development team lead is arguing that the deployment met all specifications and has
provided evidence of the client's specifications
What should the project manager do?
Show answerHide answer
Correct answer: BReview the requirements traceability matrix with the team lead and the client to
adequately resolve the issue
Question 299Choose 1
A project manager wants to make sure that similar projects in the future use the project's
performance data as a reference. However, the project manager is not sure how to
accomplish this.
What should the project manager do?
Show answerHide answer
Correct answer: DKeep project artifacts up-to-date and accessible to all stakeholders.
Question 300Choose 1
A project manager is working toward a deadline to prepare a client report. The project
manager prepared a meeting agenda but not a single meeting has gone according to plan
True, meetings always end in arguments and no action items come out of it. The project
manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
Show answerHide answer
Correct answer: CTeam charter
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.