Question 291 Choose 1
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online, yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?
Show answerHide answer

Correct answer: C Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

Question 292 Choose 1
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?
Show answerHide answer

Correct answer: D Liaise with the school to include nonworking project hours during school start and finish times

Question 293 Choose 1
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document.

What should the project manager do to avoid a delay in the project?
Show answerHide answer

Correct answer: D Begin discussions with other functional managers and meet with the accounting manager later.

Question 294 Choose 1
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?
Show answerHide answer

Correct answer: C Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

Question 295 Choose 1
Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?
Show answerHide answer

Correct answer: C Invest in coaching and training for all project team members.

Question 296 Choose 1
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?
Show answerHide answer

Correct answer: B Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

Question 297 Choose 1
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be enough to add business value.

With the project on a fixed budget, what should the project manager do next?
Show answerHide answer

Correct answer: B Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

Question 298 Choose 1
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?
Show answerHide answer

Correct answer: B Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

Question 299 Choose 1
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?
Show answerHide answer

Correct answer: D Keep project artifacts up-to-date and accessible to all stakeholders.

Question 300 Choose 1
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?
Show answerHide answer

Correct answer: C Team charter

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt