A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client's security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client's team. The
project manager does not want to have such an external dependency.
What should the project manager do first?
Show answerHide answer
Correct answer: DDocument the client's responsibility for the integration with the security subsystem.
Question 172Choose 1
A regulatory branch of an environmental government agency has recently placed a ban on
the manufacturing of a specified thickness of plastic packaging products. This ban will take
effect in 12 months. The project manager for a startup firm working in alternative packaging
has been monitoring the progress of this law for a while and. as part of the risk
management, has identified new products that can support a growing customer base.
What should the project manager do next?
Show answerHide answer
Correct answer: CInform management of the new law as an opportunity to expand market share and share
the proposed products
Question 173Choose 1
A company made several changes recently, which resulted in a positive change in
the company culture. A project manager was just assigned to report to a new project
supervisor whose leadership style is about getting things done quickly regardless of
employee
and operational impacts. Some employees are complaining about this.
What should the project manager do?
Show answerHide answer
Correct answer: AClarify expectations by explaining the company culture with the supervisor.
Question 174Choose 1
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this
individual's participation decreases, and activities that they were responsible for are not
being completed within the planned period.
What should the project manager do?
Show answerHide answer
Correct answer: BSchedule a meeting to discuss recent observations with the team member.
Question 175Choose 1
A project manager is managing a government project that targets the development of
small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal
governments will not authorize the training. As a result of the delay, project implementation
is at risk.
What is a probable reason for this?
Show answerHide answer
Correct answer: BThe project did not identify and engage the correct stakeholders.
Question 176Choose 1
During a product demo with key stakeholders, the team identifies that one of the
functionalities failed to perform as expected What should the project manager have the
project team do first to address the issue?
Show answerHide answer
Correct answer: CPerform a root cause analysis
Question 177Choose 1
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
Show answerHide answer
Correct answer: AChange management plan
Question 178Choose 1
At the end of a project, one of the suppliers is facing financial difficulties and is
pushing the project manager to obtain financial, legal, and administrative approval in order
to
communicate formal project closure and ensure the transfer of liability. What should the
project manager do next?
Show answerHide answer
Correct answer: ACompare the achieved results to the contract requirements.
Question 179Choose 1
A system migration project is in its closing stage. The project manager is being pressured
to close the project The project manager communicated to all stakeholders; however, the
last department to migrate indicated that they have not received the notification
What should the project manager do?
Show answerHide answer
Correct answer: DLog the issue and assign it to the project team member(s).
Question 180Choose 1
A project manager is asked to implement a hybrid approach that will replace a predictive
approach on an upcoming project How should the project manager adjust their
responsibilities accordingly?
Show answerHide answer
Correct answer: ABecome a servant leader by supporting team collaboration and removing impediments
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.