Question 171 Choose 1
A project team that is very experienced in enterprise resource planning (ERP) systems implementation is currently planning the delivery of a new ERP project. There is a requirement to reuse the client's security subsystem developed by a third party. The client states that integration with the security subsystem must be done by the client's team. The project manager does not want to have such an external dependency.

What should the project manager do first?
Show answerHide answer

Correct answer: D Document the client's responsibility for the integration with the security subsystem.

Question 172 Choose 1
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?
Show answerHide answer

Correct answer: C Inform management of the new law as an opportunity to expand market share and share the proposed products

Question 173 Choose 1
A company made several changes recently, which resulted in a positive change in the company culture. A project manager was just assigned to report to a new project supervisor whose leadership style is about getting things done quickly regardless of employee and operational impacts. Some employees are complaining about this.

What should the project manager do?
Show answerHide answer

Correct answer: A Clarify expectations by explaining the company culture with the supervisor.

Question 174 Choose 1
A key project team member has exhibited high interest in a project. The input from this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?
Show answerHide answer

Correct answer: B Schedule a meeting to discuss recent observations with the team member.

Question 175 Choose 1
A project manager is managing a government project that targets the development of small businesses in remote towns. The project team is having difficulty conducting entrepreneurship training in some of the targeted towns because the local municipal governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?
Show answerHide answer

Correct answer: B The project did not identify and engage the correct stakeholders.

Question 176 Choose 1
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?
Show answerHide answer

Correct answer: C Perform a root cause analysis

Question 177 Choose 1
During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a minimal storage room. The sponsor insists on making this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?
Show answerHide answer

Correct answer: A Change management plan

Question 178 Choose 1
At the end of a project, one of the suppliers is facing financial difficulties and is pushing the project manager to obtain financial, legal, and administrative approval in order to communicate formal project closure and ensure the transfer of liability. What should the project manager do next?
Show answerHide answer

Correct answer: A Compare the achieved results to the contract requirements.

Question 179 Choose 1
A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?
Show answerHide answer

Correct answer: D Log the issue and assign it to the project team member(s).

Question 180 Choose 1
A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?
Show answerHide answer

Correct answer: A Become a servant leader by supporting team collaboration and removing impediments

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt