An agile team was hired to work on a public service project. The team received a
list of vague ideas about the business and now needs to understand, develop, and
prioritize a
list of functionalities.
Who will be responsible for this task?
Show answerHide answer
Correct answer: DProduct owner
Question 202Choose 1
During project execution a project team member resigned and a new junior member joined
the team To smooth the transition the project manager assigned a senior project team
member to transfer knowledge and support the junior team member The project manager
subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team
However the project manager checked that deliverable and found it met quality
requirements
Which technique should the project manager use to resolve this issue?
Show answerHide answer
Correct answer: DCollaborate/problem solve
Question 203Choose 1
A project team with a tight schedule has succeeded in maintaining a schedule performance
index (SPI) of the through regular daily standups and overtime, when required After a few
months the project manager notices that some of the team members' performance has
decreased but mat the overall project team performance is still ahead of schedule by a few
days
What should the project manager do first to maintain the project team's performance level?
Show answerHide answer
Correct answer: DProvide routine mentoring and coaching to the team members to identify any
demotivating issues
Question 204Choose 1
A project manager recognizes that a key stakeholder is not engaged in the project and
does not seem interested in the project status. The project manager is concerned that the
project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
Show answerHide answer
Correct answer: AAnalyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success
Question 205Choose 1
A project manager is leading the first agile project for the organization. During the
kick-off meeting, the project manager notices that the team does not have the same
understanding about agile approaches. The project manager is concerned about the impact
of that confusion.
What should the project manager do to address this situation?
Show answerHide answer
Correct answer: CMentor the team to explain agile principles and create a shared understanding.
Question 206Choose 1
A project manager is leading a software development project. Recently, team members
have complained that during the last few dally standup meetings, a key stakeholder
frequently interrupts, requests explanations, and proposes unplanned changes. This issue
is frustrating the project team and slowing down me work.
What should the project manager do?
Show answerHide answer
Correct answer: DAddress the issue with the stakeholder and explain the situation.
Question 207Choose 1
A project to implement a new process is still in development. When implemented,
the company will benefit by a reduction in utility costs. The project financial evaluation
indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
Show answerHide answer
Correct answer: AIncrease resources on the technical design to enable a decision to proceed as this is
aquick return project.
Question 208
A retail company identifies that it is losing sales because customers are not promptly
informed about promotions and sales points. The company needs to react quickly. A
project charter is created along with requests to develop a mobile application for the
customer. The marketing department has a long list of features to add to the application,
but there are no specifications.
Considering the objective to deploy customer value, which project life cycle approach
should be chosen?
Show answerHide answer
Explanation
Question 209Choose 1
A project manager notices that the response action for an identified issue is insufficient for
solving the problem What should the project manager do next?
Show answerHide answer
Correct answer: DMeet with the project team to find another solution
Question 210Choose 1
During the planning for a long project, the project manager recognized that several
members of the team are new to their roles. How should the project manager incorporate
this
into planning?
Show answerHide answer
Correct answer: CAssess the training requirements and ensure time for professional developmenttraining
by senior members.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.