Question 201 Choose 1
An agile team was hired to work on a public service project. The team received a list of vague ideas about the business and now needs to understand, develop, and prioritize a list of functionalities.

Who will be responsible for this task?
Show answerHide answer

Correct answer: D Product owner

Question 202 Choose 1
During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?
Show answerHide answer

Correct answer: D Collaborate/problem solve

Question 203 Choose 1
A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?
Show answerHide answer

Correct answer: D Provide routine mentoring and coaching to the team members to identify any demotivating issues

Question 204 Choose 1
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?
Show answerHide answer

Correct answer: A Analyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success

Question 205 Choose 1
A project manager is leading the first agile project for the organization. During the kick-off meeting, the project manager notices that the team does not have the same understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?
Show answerHide answer

Correct answer: C Mentor the team to explain agile principles and create a shared understanding.

Question 206 Choose 1
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?
Show answerHide answer

Correct answer: D Address the issue with the stakeholder and explain the situation.

Question 207 Choose 1
A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?
Show answerHide answer

Correct answer: A Increase resources on the technical design to enable a decision to proceed as this is aquick return project.

Question 208
A retail company identifies that it is losing sales because customers are not promptly informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?
Show answerHide answer

Explanation

Question 209 Choose 1
A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
Show answerHide answer

Correct answer: D Meet with the project team to find another solution

Question 210 Choose 1
During the planning for a long project, the project manager recognized that several members of the team are new to their roles. How should the project manager incorporate this into planning?
Show answerHide answer

Correct answer: C Assess the training requirements and ensure time for professional developmenttraining by senior members.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt