During the execution phase of a project a new project manager is assigned to replace the
previous project manager As the project manager starts managing the project, they
discover that team performance is significantly decreasing, which is impacting the project's
key performance indicators (KPIs). This team has delivered good performance on similar
projects in the past
What should the project manager do next to improve this situation?
Show answerHide answer
Correct answer: ACall for a team meeting to identify the root cause for the declining performance
Question 152Choose 1
An organization has recently decided to switch from a predictive to an agile delivery
approach. The one ongoing project will still be led by a project manager. The agile teams
for that project have not produced any documentation.
What should the project manager of the ongoing project do?
Show answerHide answer
Correct answer: CCheck with the agile teams to see if the project manager's understanding of the Agile
Manifesto is correct.
Question 153Choose 1
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of
stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
Show answerHide answer
Correct answer: ADiscuss the issue with all stakeholders and work on a communications management
plan to meet all stakeholder requirements.
Question 154Choose 1
An agile project is running its second of six iterations. One new team member who does
not have agile experience has just joined the team. In the daily meetings, the project
manager observes that the team is having problems meeting their goals.
What should the project manager do?
Show answerHide answer
Correct answer: AProvide feedback to the team and conduct a meeting to review the team rules.
Question 155Choose 1
A project is delayed due to an undelivered component, which was caused by a conflict
between the procurement lead and the contracts manager. The project manager
schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?
Show answerHide answer
Correct answer: BMediator
Question 156Choose 1
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is
a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
Show answerHide answer
Correct answer: DMeet the team member and try to plan a course of action together.
Question 157Choose 1
A global company is executing a strategic project to upgrade a legacy enterprise system.
The company uses a hybrid approach to project management and has just completed the
first sprint A team member provided ideas to improve the testing process during the sprint
retrospective.
What is the next step for the project manager?
Show answerHide answer
Correct answer: ADocument the lessons learned and implement improvements in the next sprint
Question 158Choose 1
A project manager has just taken over a project that is halfway through its schedule. In a
brief meeting with the client’s key project team, the project manager receives several
requests from a specific client team member who was not at the project team meeting. The
requests for information seem to be for trivial information that was previously submitted in
project documents.
What should the project manager do first?
Show answerHide answer
Correct answer: BReview the stakeholder register to gain insight into the expectations of that team
member.
Question 159Choose 1
A project manager is leading a product development project that requires high involvement
from several stakeholders. What should the project manager do to ensure this
involvement?
Show answerHide answer
Correct answer: AEvaluate the engagement needs of stakeholders.
Question 160Choose 1
A project manager is assigned to a new project. Many of the project deliverables need to
be outsourced.
What should the project manager use to document the project deliverables?
Show answerHide answer
Correct answer: BStatement of work (SOW)