During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?
Show answerHide answer

Correct answer: A Call for a team meeting to identify the root cause for the declining performance

Question 152 Choose 1
An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?
Show answerHide answer

Correct answer: C Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

Question 153 Choose 1
In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the project sponsor that they know very little about the project.

What should the project manager do?
Show answerHide answer

Correct answer: A Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

Question 154 Choose 1
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?
Show answerHide answer

Correct answer: A Provide feedback to the team and conduct a meeting to review the team rules.

Question 155 Choose 1
A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?
Show answerHide answer

Correct answer: B Mediator

Question 156 Choose 1
A newly hired team member just joined the project team and reports directly to the project manager. In the first week, this new member tells the project manager that there is a task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?
Show answerHide answer

Correct answer: D Meet the team member and try to plan a course of action together.

Question 157 Choose 1
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?
Show answerHide answer

Correct answer: A Document the lessons learned and implement improvements in the next sprint

Question 158 Choose 1
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?
Show answerHide answer

Correct answer: B Review the stakeholder register to gain insight into the expectations of that team member.

Question 159 Choose 1
A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?
Show answerHide answer

Correct answer: A Evaluate the engagement needs of stakeholders.

Question 160 Choose 1
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?
Show answerHide answer

Correct answer: B Statement of work (SOW)

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt