Question 141 Choose 1
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager do with many tasks still open on the Kanban board?
Show answerHide answer

Correct answer: B Discuss the impact of starting the item with the team.

Question 142 Choose 1
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?
Show answerHide answer

Correct answer: B Analyze both projects to determine the most effective use of common resources

Question 143 Choose 1
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?
Show answerHide answer

Correct answer: B Review the operations manager's concerns and ensure these concerns are addressed

Question 144 Choose 1
A project manager is assigned to oversee the deployment of a new product that will be used by the entire organization. A key success factor for the project is the timely and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?
Show answerHide answer

Correct answer: D Engage in creative and iterative negotiations with the leaders of each entity toagree on the launch date.

Question 145 Choose 1
A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?
Show answerHide answer

Correct answer: D Burndown chart

Question 146
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.
Show answerHide answer

Explanation

Question 147 Choose 1
A stakeholder is requesting that the project manager share project status updates on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?
Show answerHide answer

Correct answer: C Review the stakeholder engagement and communications management plans.

Question 148 Choose 1
A project management team received news that a competitor has released the latest version of a program. What should the team do next?
Show answerHide answer

Correct answer: A Review the project plan to evaluate if any updates should be made.

Question 149 Choose 2
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)
Show answerHide answer

Correct answer: C, D Perform a risk identification process with the project team.Consult with the project stakeholders.

Question 150 Choose 1
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
Show answerHide answer

Correct answer: D Validate the proposed change's impact on the project.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt