A new privacy law will go into effect at the beginning of the next calendar year. The project
manager realizes the project needs to be compliant with the new law. What should the
project manager do next?
Show answerHide answer
Correct answer: BInform the project team and create a spike for the next Iteration.
Question 182Choose 1
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification
for the product.
What should the project manager do to proceed with the project management plan?
Show answerHide answer
Correct answer: CRecommend to the project sponsor that a predictive approach is appropriate for
theproject due to the stable product requirements.
Question 183Choose 1
During the sprint planning of a project, the team members have a disagreement
about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?
Show answerHide answer
Correct answer: DFacilitate the discussion so that the team members can reach a consensus.
Question 184Choose 1
In an agile team, some of the team members are coming forward to ask for more
autonomy on the project. What should the project manager do in this situation?
Show answerHide answer
Correct answer: AEncourage the team members to make decisions.
Question 185Choose 1
A project manager is working with an agile team to enhance a product. Due to a
tight deadline, the team is trying to crash the schedule by engaging multiple resources to
work
on the project simultaneously. However, the technical environment is configured to allow
only
one resource to work on a feature at a time. The team plans to upgrade the technical environment but is unable to agree on a way forward.
What should the project manager do first?
Show answerHide answer
Correct answer: AConduct a consensus-building session to decide how to approach the next set of work.
Question 186Choose 1
An agile project manager has learn members from different continents on the project team.
During the dairy scrum meetings the project manager notices that there are gaps in
understanding about the project goals and objectives
What should the project manager do?
Show answerHide answer
Correct answer: CConduct a kick-off meeting and communicate the goals and objectives of the project
Question 187Choose 1
A contract has fust been awarded for an automation project that was supported by the local
community. The project manager was warned by the elected officials that the project
cannot proceed.
Why did this action occur?
Show answerHide answer
Correct answer: DLack of a proper legal framework in place
Question 188Choose 1
During the early phases of a project, mitigation actions were not executed in a
timely manner; therefore, the project schedule was impacted. Several project stakeholders
are
now frustrated with the delays.
What should the project manager have done to manage the issue?
Show answerHide answer
Correct answer: CIdentified the appropriate response and had it implemented
Question 189Choose 1
A project manager realizes that the team members are new to the hybrid approach and do
not value standup meetings. Team members often arrive late. Digress into solutioning. or
skip the meetings altogether.
How should the project manager improve this situation with the project team?
Show answerHide answer
Correct answer: AEngage the project team In implementing and Improving key aspects of the standup
meetings.
Question 190Choose 1
A project manager has recently joined a small company. The company's chief
operating officer (COO) asked the team to skip some steps in the process in order to work more quickly. The project manager wants to ensure that these steps are not skipped in the
future.
What should the project manager do?
Show answerHide answer
Correct answer: ANotify all team members that all steps in the process must be completed.