An international client contacted a software development company to build out a
software product, and an agile project manager was assigned. At one of the review
meetings,
the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
Show answerHide answer
Correct answer: DTreat it as a change request and assess the effect on the project's goals.
Question 192Choose 1
A team member is always late to work. The project manager is concerned that this may
affect the motivation of other team members The project manager tells the new team
member to align with the team's principles and arrive on time
What kind of conflict resolution did the project manager apply in this situation?
Show answerHide answer
Correct answer: DForce/direct
Question 193Choose 1
An organization is producing a product using a hybrid approach with several phases. Some
of the phases are planned to be executed in predictive and some in agile. During the agile
phase, the project manager notices that the team members sometimes unknowingly work
on the same task.
What should the project manager do?
Show answerHide answer
Correct answer: ACommunicate the task assignments to the team members in a clear manner.
Question 194Choose 1
In a hybrid project, 100 new base stations are being added to a 4G mobile network
every month. At the end of the first month, the team is behind the target and the operator is
losing money. The stakeholders are requesting information on when the base stations can
go
live and begin to bill.
What should the project manager do to take the schedule back and accelerate the return
on
investment (ROI) of the project?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1
week.
What should the project manager do to benefit from the SME's presence?
Show answerHide answer
Correct answer: CMeet with the SME to discuss the current challenges the team is facing.
Question 196Choose 1
A project manager has heard about the large volume of emails the team receives each day
which prevents them from doing project work. One team member has stated that they
would like to be able to access project-related information when needed
To what type of communication is the team member referring?
Show answerHide answer
Correct answer: CPull communication
Question 197Choose 1
During the executing phase, a project manager is reviewing the issue log and finds
there are outstanding high-priority issues that are still open. Most of the open issues
require
effort from external domain experts who are not on the project team.
What should the project manager do?
Show answerHide answer
Correct answer: BReview the open issues with the issue reporter and issue a change request to hire
anexternal domain expert.
Question 198Choose 1
A project manager has been assigned to a project that is in progress. The project
manager is looking for information regarding why the project is being completed.
What should the project manager do first?
Show answerHide answer
Correct answer: CUnderstand the project success criteria and objectives.
Question 199Choose 1
A project manager is assigned to a digital transformation project for a bank. The company
culture is conservative and resistant to transformation or innovation. What should the
project manager do first to support the transformation''
Show answerHide answer
Correct answer: CProvide proper training sessions to the stakeholders so they understand the purpose of
the change
Question 200Choose 1
A project manager Is working on the initial phases of a highly technical project that employs
the "first of its kind" technology. Many of the key project stakeholders are unaware of the
project objectives and their participation levels are poor. At every meeting, there are a lot of
objections and queries raised that are taking the discussions to a different level, and a
great deal of time is wasted
What should the project manager do?
Show answerHide answer
Correct answer: CPlan to conduct informal sessions with the stakeholders.