PMI certification · Exam PMP

PMP Mock Exam Page 20

Project Management Professional (PMP) July 2026 Update

Free PMP mock exam questions 191–200, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Free PMP questions

191–200 of 636 free
Question 191 Choose 1
An international client contacted a software development company to build out a software product, and an agile project manager was assigned. At one of the review meetings, the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?
Show answerHide answer

Correct answer: D Treat it as a change request and assess the effect on the project's goals.

Question 192 Choose 1
A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?
Show answerHide answer

Correct answer: D Force/direct

Question 193 Choose 1
An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?
Show answerHide answer

Correct answer: A Communicate the task assignments to the team members in a clear manner.

Question 194 Choose 1
In a hybrid project, 100 new base stations are being added to a 4G mobile network every month. At the end of the first month, the team is behind the target and the operator is losing money. The stakeholders are requesting information on when the base stations can go live and begin to bill.

What should the project manager do to take the schedule back and accelerate the return on investment (ROI) of the project?
Show answerHide answer

Correct answer: D Reconsider necessary schedule reserves.

Question 195 Choose 1
A project team is facing challenges understanding how to deliver a project's scope. A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?
Show answerHide answer

Correct answer: C Meet with the SME to discuss the current challenges the team is facing.

Question 196 Choose 1
A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?
Show answerHide answer

Correct answer: C Pull communication

Question 197 Choose 1
During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team.

What should the project manager do?
Show answerHide answer

Correct answer: B Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

Question 198 Choose 1
A project manager has been assigned to a project that is in progress. The project manager is looking for information regarding why the project is being completed.

What should the project manager do first?
Show answerHide answer

Correct answer: C Understand the project success criteria and objectives.

Question 199 Choose 1
A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''
Show answerHide answer

Correct answer: C Provide proper training sessions to the stakeholders so they understand the purpose of the change

Question 200 Choose 1
A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?
Show answerHide answer

Correct answer: C Plan to conduct informal sessions with the stakeholders.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt