Question 161 Choose 1
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
Show answerHide answer

Correct answer: D Initiate a review of the procedures with the CTO and the team.

Question 162 Choose 1
A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?
Show answerHide answer

Correct answer: C Identified key stakeholders and included all of them in project agreement discussions.

Question 163 Choose 1
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?
Show answerHide answer

Correct answer: D Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Question 164 Choose 3
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
Show answerHide answer

Correct answer: A, C, E High-level product backlogProduct visionProduct roadmap

Question 165
A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.
Show answerHide answer

Explanation

Question 166 Choose 2
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
Show answerHide answer

Correct answer: A, D Host a special meeting to talk about what happened.Conduct a team-building workshop.

Question 167 Choose 1
A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?
Show answerHide answer

Correct answer: D Documented the technical reviews with the new change

Question 168 Choose 1
A project manager is working with a team that is new to agile. One of the more influential stakeholders struggles with the nature of agile. The project manager knows that this stakeholder is needed as an advocate and wants to do everything possible to make the stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's performance?
Show answerHide answer

Correct answer: D Earned value analysis (EVA)

Question 169 Choose 1
An equipment vendor will implement a new production line for a client company. The year- long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?
Show answerHide answer

Correct answer: C Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

Question 170 Choose 1
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?
Show answerHide answer

Correct answer: B agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt