Free PMP mock exam questions 131–140, each with the answer and an explanation.

20 questions · 26 minutes · free, no sign-up

Free PMP questions

131–140 of 636 free
Question 131 Choose 1
The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?
Show answerHide answer

Correct answer: A Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

Question 132 Choose 1
A company is transitioning from a predictive to agile delivery of projects. Based on the requirements, the project team estimates the budget and decides to use a fixed-price contract with its vendor. However, during the execution of the project, the requirements evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?
Show answerHide answer

Correct answer: C Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

Question 133 Choose 1
An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?
Show answerHide answer

Correct answer: D Support the team members' growth and development.

Question 134 Choose 1
A supplier was supposed to mobilize a government-issued, licensed piece of equipment two days ago, but did not. The procurement manager was informed that the supplier failed to check the validity of the license, which expired last week. The supplier had already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?
Show answerHide answer

Correct answer: C Review the terms of the contract in order to determine next steps.

Question 135 Choose 1
At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?
Show answerHide answer

Correct answer: B Set up information review sessions before reconvening another approval session.

Question 136 Choose 1
A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?
Show answerHide answer

Correct answer: C Describe to the team members how specific tools and techniques can be used to finish on time

Question 137 Choose 1
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?
Show answerHide answer

Correct answer: A Analyzed the sponsor's communication requirements.

Question 138 Choose 1
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?
Show answerHide answer

Correct answer: C Schedule a kick-off session to explain the problems of the project and gain approval and support

Question 139 Choose 1
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not delivered, the company could receive a fine from the government. What should the project manager do?
Show answerHide answer

Correct answer: B Review the resources required for the tasks on the critical path.

Question 140 Choose 1
A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?
Show answerHide answer

Correct answer: B Use a problem-solving approach and set up a discussion with the team lead and team member.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.