When reviewing the project team's performance the project manager realizes that the team
velocity is not fast enough to meet the next review gate goal What should the project
manager do?
Show answerHide answer
Correct answer: DUse the standup meeting to assess impediments and problems
Question 122Choose 1
A project manager is attending a progress meeting with a client The client requests a
design change which might potentially add value to the project What action should the
project manager take?
Show answerHide answer
Correct answer: DMake transactional decisions focusing on the project goals
Question 123Choose 1
A project manager for an agile project wants to have a highly engaged team. How should
the project manager achieve this objective?
Show answerHide answer
Correct answer: BPromote an environment where everybody knows what their contribution means to the
project as a whole.
Question 124Choose 1
A project manager is hired by a global company. The project manager is an agile specialist
and is tasked with supporting the project team to reduce rework and dissatisfaction.
How should the project manager address these objectives?
Show answerHide answer
Correct answer: CAdopt an incremental cycle of delivering value to the customer.
Question 125Choose 1
local company is developing a new product and. for the first time, using a remote
team for the programming tasks of features. The design for the product comes from the
local team. During the third sprint review, the product owner has concerns about the
project's
outcomes. The remote development team is complaining that they do not clearly
understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
Show answerHide answer
Correct answer: DDetermine the communication needs, environment, and tools to get the message
across.
Question 126Choose 1
A company has agreed to run a transformation project using agile approaches.
During the implementation, there is pushback from the functional groups that the project is
moving too fast.
What should the project manager have done at the beginning of the project to prevent this
from happening?
Show answerHide answer
Correct answer: BAssessed the organizational culture
Question 127
Match the project situation on the left to the meeting on the right where the situation could
occur.
Show answerHide answer
Explanation
Question 128Choose 1
A key agile project team member takes a leave of absence in the middle of an iteration and
will not return to work for a while What should the project manager do next regarding the
feature on which the team member was working?
Show answerHide answer
Correct answer: DReview the work in progress with the product owner to determine the next step
Question 129Choose 1
A project manager has been assigned to take over an existing software project. The project
manager inherited a lean team comprised of key stakeholders, subject matter experts
(SMEs), and senior developers. While reviewing the project status with the team, the
project manager observes that the team seems to lack direction and enthusiasm.
What should the new project manager do?
Show answerHide answer
Correct answer: DEncourage participation in decision making and empower the team.
Question 130Choose 1
An agile team is working on a product deliverable in an organization that is transforming
itself to quickly respond to change. The finance
team is requesting a project budget for the new product.
What should the team do to address this request?
Show answerHide answer
Correct answer: AWork with the finance team to transition to incremental budgeting.