Question 111 Choose 1
The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project. How should the project manager handle this request?
Show answerHide answer

Correct answer: D Validate if the training is within scope and budget.

Question 112 Choose 1
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?
Show answerHide answer

Correct answer: C Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

Question 113 Choose 1
A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?
Show answerHide answer

Correct answer: D Offer cross-training and mentoring to the new team member

Question 114 Choose 1
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
Show answerHide answer

Correct answer: A Determine a leadership style that is suitable for that location.

Question 115 Choose 1
A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?
Show answerHide answer

Correct answer: B Perform quality assurance to review the processes against the quality management plan and identify gaps.

Question 116 Choose 1
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?
Show answerHide answer

Correct answer: C Allocated additional time for mentoring

Question 117 Choose 1
An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?
Show answerHide answer

Correct answer: B Plan projectA in sprints, starting with the module that does not require machine learning skills.

Question 118 Choose 2
Due to a recent budget reduction, two team members were released from an agile team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations?
(Choose two)
Show answerHide answer

Correct answer: A, B Ask the agile team to review the updated sprint velocity with the customer.Ask the product owner to review the prioritized backlog with the customer.

Question 119 Choose 1
A project manager for a building construction project is planning to go on vacation midway through the project execution phase. What should the project manager do first to ensure the team is empowered and deadlines are met?
Show answerHide answer

Correct answer: D Analyze the impacts and create a plan for team decision making

Question 120 Choose 1
A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''
Show answerHide answer

Correct answer: D The project is under budget and on schedule.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt