The project manager has recently received funding approval for a training program
for the entire project team but has not yet defined the most effective training course. One
team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?
Show answerHide answer
Correct answer: DValidate if the training is within scope and budget.
Question 112Choose 1
A business analyst on the project meets the customer in the elevator and says that due to
constant changes in requirements the development of the product will take more time than
expected What should the project manager do?
Show answerHide answer
Correct answer: CPoint out to the project team and the customer that all information concerning the
timeline of the project should be communicated by the project manager.
Question 113Choose 1
A highly skilled team resource received a job offer and is leaving the project soon What
should the project manager do to maintain project performance while a new team member
is being onboarded?
Show answerHide answer
Correct answer: DOffer cross-training and mentoring to the new team member
Question 114Choose 1
A project manager is transferred to another country to perform a project within their
organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
Show answerHide answer
Correct answer: ADetermine a leadership style that is suitable for that location.
Question 115Choose 1
A project is successfully delivering its product outcomes, and the customer satisfaction
rating is high. However, during an internal audit, it is discovered that certain essential
process documents and approvals are missing, and the project is evaluated as being
noncompliant.
What should the project manager do next?
Show answerHide answer
Correct answer: BPerform quality assurance to review the processes against the quality management plan
and identify gaps.
Question 116Choose 1
An intern is replacing a critical resource midway through a sprint To help the intern get up
to speed, the project manager assigns a senior engineer in the team as the intern's mentor
Two months later, the project goes into critical status, delaying the release milestone by a
month.
What should the project manager have done to avoid this scenario?
Show answerHide answer
Correct answer: CAllocated additional time for mentoring
Question 117Choose 1
An organization uses a hybrid approach to project management. A project manager has
been assigned to an external project, project A, where two of the three modules in the
project require machine learning skills. The only machine learning expert in the project
manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
Show answerHide answer
Correct answer: BPlan projectA in sprints, starting with the module that does not require machine learning
skills.
Question 118Choose 2
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations?
(Choose
two)
Show answerHide answer
Correct answer: A, BAsk the agile team to review the updated sprint velocity with the customer.Ask the product owner to review the prioritized backlog with the customer.
Question 119Choose 1
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
Show answerHide answer
Correct answer: DAnalyze the impacts and create a plan for team decision making
Question 120Choose 1
A project manager is in the middle of an agile project comprised of 100 user stories broken
down into five iterations Each user story is worth USS50 The actual expenditure is
US$2,000 and 50 user stories have been delivered.
Which statement is true''
Show answerHide answer
Correct answer: DThe project is under budget and on schedule.
Full mock exam
Sit the PMP exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.