A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
Show answerHide answer
Correct answer: BInclude knowledge transfer sessions between the project and operations teams at every
stage.
Question 102Choose 1
During a project status update by the project management office (PMO), the CEO is
concerned that the status of all projects suddenly changed from green to red, without
warning. Upper management is used to reading traditional reports related to progress and
cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?
Show answerHide answer
Correct answer: BExplore reporting the earned value (EV) key performance indicators (KPls) using agile
progress as an input.
Question 103Choose 1
The project manager of a hybrid project learns that a stakeholder has approached a team
member directly to request a change This change will impact the project m a significant
way The project manager should ten the stakeholder that the correct procedure tor new
requirements is to provide a request directly to whom?
Show answerHide answer
Correct answer: AProduct owner
Question 104Choose 1
A project manager finds that team members In an agile project are involved in several
different projects due to budget constraints. What should the project manager do?
Show answerHide answer
Correct answer: ARequest the project sponsor prioritize and if necessary, allocate additional budget so the
team can work on a single project
Question 105Choose 1
A key team member shared confidential information about another team member with
management, a practice that is against ethical standards. During a team meeting, some of
the team members requested that the key team member be removed from the team.
What should the project manager do next?
Show answerHide answer
Correct answer: BSpeak with the key team member to clarify the situation.
Question 106Choose 1
A new team member on a self-organizing team is finding it difficult to deliver due to the new
technology being used in the project. What should the project manager do in this situation?
Show answerHide answer
Correct answer: CMentor the team member and provide the necessary training.
Question 107Choose 1
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
Show answerHide answer
Correct answer: AAssess the current state process to define the scope of the digitization.
Question 108Choose 1
A junior team member escalates an issue to the project manager about another
member's interpersonal skills causing the team to be less effective.
What should the project manager do first?
Show answerHide answer
Correct answer: CGather information and find the root cause of the problem.
Question 109Choose 1
A project manager is managing a project aimed at providing incremental deliveries to the
market every three months. The team has been assigned, and the product backlog was
created and prioritized by the product owner. After four iterations, the product owner
escalates complaints to the CEO because the product does not meet the product owner's
expectations.
What should the project manager have done to prevent this situation from happening?
Show answerHide answer
Correct answer: AImplemented sprint reviews with the product owner and retrospectives with the team to
minimize gaps
Question 110Choose 1
A project manager is leading an agile project in an organization that has not executed this
type of project before. In order to ensure the project is following the compliance
requirements, what should the project manager do?
Show answerHide answer
Correct answer: CMeet with the project management office (PMO)/compliance entity to work onprocess
tailoring to ensure that the agile deliverables support the compliance requirements of the
organization.