Question 101 Choose 1
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?
Show answerHide answer

Correct answer: B Include knowledge transfer sessions between the project and operations teams at every stage.

Question 102 Choose 1
During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?
Show answerHide answer

Correct answer: B Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

Question 103 Choose 1
The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
Show answerHide answer

Correct answer: A Product owner

Question 104 Choose 1
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
Show answerHide answer

Correct answer: A Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

Question 105 Choose 1
A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?
Show answerHide answer

Correct answer: B Speak with the key team member to clarify the situation.

Question 106 Choose 1
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
Show answerHide answer

Correct answer: C Mentor the team member and provide the necessary training.

Question 107 Choose 1
A company is planning a digitization project. Which action should the project manager take first when defining the project scope?
Show answerHide answer

Correct answer: A Assess the current state process to define the scope of the digitization.

Question 108 Choose 1
A junior team member escalates an issue to the project manager about another member's interpersonal skills causing the team to be less effective.

What should the project manager do first?
Show answerHide answer

Correct answer: C Gather information and find the root cause of the problem.

Question 109 Choose 1
A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?
Show answerHide answer

Correct answer: A Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

Question 110 Choose 1
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
Show answerHide answer

Correct answer: C Meet with the project management office (PMO)/compliance entity to work onprocess tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt