Question 91 Choose 1
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
Show answerHide answer

Correct answer: D Ask an experienced team member to coach the new team member

Question 92 Choose 1
A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?
Show answerHide answer

Correct answer: D Provide the business analyst with access to the financial and scheduling information

Question 93 Choose 1
One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?
Show answerHide answer

Correct answer: D Execute a contingency plan to address the issue with the vendor

Question 94 Choose 1
During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?
Show answerHide answer

Correct answer: D In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Question 95 Choose 1
During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?
Show answerHide answer

Correct answer: D Ask the product owner to prioritize the item with the customer

Question 96 Choose 1
During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?
Show answerHide answer

Correct answer: D Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Question 97 Choose 1
A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?
Show answerHide answer

Correct answer: B Ask the team member to work with their peers to knowledge share

Question 98 Choose 1
During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?
Show answerHide answer

Correct answer: C Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

Question 99 Choose 1
Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?
Show answerHide answer

Correct answer: A Schedule a meeting between the team members to find a solution.

Question 100 Choose 1
A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?
Show answerHide answer

Correct answer: C Set expectations with the new team member and explain what is needed

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt