Question 81 Choose 1
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
Show answerHide answer

Correct answer: A A release burndown chart

Question 82 Choose 1
A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?
Show answerHide answer

Correct answer: B A leadership style that coaches people who want help and fosters greater team collaboration

Question 83 Choose 1
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?
Show answerHide answer

Correct answer: C Validated the project artifacts

Question 84 Choose 1
A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?
Show answerHide answer

Correct answer: A Hold a stakeholder meeting to align timelines and scope expectations.

Question 85 Choose 1
During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?
Show answerHide answer

Correct answer: A Update project documents to include adaptive tools and artifacts and plan the first iterative session

Question 86 Choose 1
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?
Show answerHide answer

Correct answer: D Used the resource management plan to identify the impacts of the other projects

Question 87 Choose 2
During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)
Show answerHide answer

Correct answer: A, C Encourage all team members to use a virtual workspaceTalk to the team member about their engagement and take appropriate action.

Question 88 Choose 1
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?
Show answerHide answer

Correct answer: D The WBS dictionary

Question 89 Choose 1
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?
Show answerHide answer

Correct answer: A Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

Question 90 Choose 2
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
Show answerHide answer

Correct answer: B, D Encourage working in pairs and knowledge sharingFacilitate a training event with an external trainer

Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt