Question 71 Choose 1
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?
Show answerHide answer

Correct answer: A Personas

Question 72 Choose 1
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?
Show answerHide answer

Correct answer: B Review the new requirements with the compliance department to determine if a change request is needed.

Question 73 Choose 1
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?
Show answerHide answer

Correct answer: D Review this stakeholder's communication requirements.

Question 74 Choose 1
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?
Show answerHide answer

Correct answer: D A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Question 75 Choose 1
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?
Show answerHide answer

Correct answer: D Develop and define a communication strategy for stakeholders.

Question 76 Choose 1
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?
Show answerHide answer

Correct answer: C Comply with the regulatory requirements and work to compress the project schedule.

Question 77 Choose 1
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?
Show answerHide answer

Correct answer: B Keep the focus on the priority items while the change goes through the change control process.

Question 78 Choose 1
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?
Show answerHide answer

Correct answer: B Meet with the project sponsor to better understand the strategic benefits of the project.

Question 79 Choose 1
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
Show answerHide answer

Correct answer: D Continue with the sprint work as planned and keep monitoring.

Question 80 Choose 1
A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?
Show answerHide answer

Correct answer: D Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

That's the last free question in Topic 5: Exam Pool E

You've seen the free 30% (80 of 267 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PMP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMP mock exam
  • 180questions per mock
  • 230 mintime limit
  • 2,130questions in the bank
  • Newmock on every attempt