A project team is executing a large regulatory project comprised of a multitude of internal
and external stakeholders. An initial impact analysis revealed several systems, including an
enhancement to existing modules as well as new builds. After completion of the initial
design workshop, the team conducted a brainstorming session to better understand the
types of likely users.
Which technique will best serve this purpose?
Show answerHide answer
Correct answer: APersonas
Question 72Choose 1
A multimillion-dollar project has started and is in the execution phase. A local regulatory
authority has just announced changes to the requirements that will need to be implemented
in 6 months, prior to completing the project execution phase.
What should the project manager do next?
Show answerHide answer
Correct answer: BReview the new requirements with the compliance department to determine if a change
request is needed.
Question 73Choose 1
A project team member informs the project manager that a stakeholder is contacting the
team member to request status updates. The team member is being distracted by these
repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
Show answerHide answer
Correct answer: DReview this stakeholder's communication requirements.
Question 74Choose 1
A project manager is working with a customer's team on a new project. Some product
definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a
specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
Show answerHide answer
Correct answer: DA hybrid approach will allow for management of the requirement uncertainties as well as
the date restriction.
Question 75Choose 1
A project manager is assigned to a new project team that has several stakeholders who
can have significant influence over the project outcomes.
The project manager categorized the stakeholders into four different groups and wants to
define the communication strategy.
How should the project manager handle communication?
Show answerHide answer
Correct answer: DDevelop and define a communication strategy for stakeholders.
Question 76Choose 1
A company initiated a project to introduce a new product to the market. The product must
undergo the industry's regulatory process prior to approval and launch However, the
company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
Show answerHide answer
Correct answer: CComply with the regulatory requirements and work to compress the project schedule.
Question 77Choose 1
A project interfaces with other projects that are in the same portfolio but are being
developed in international locations. One of the international projects has suggested a
tactical change that needs to be implemented in this project.
What should the project manager do next ?
Show answerHide answer
Correct answer: BKeep the focus on the priority items while the change goes through the change control
process.
Question 78Choose 1
A project sponsor has approved the project charter and business case. The project
manager has reviewed the artifacts to initiate the project and is unclear if the intended
benefits of the project align with the strategic objectives of the business.
What should the project manager do first?
Show answerHide answer
Correct answer: BMeet with the project sponsor to better understand the strategic benefits of the project.
Question 79Choose 1
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The
burndown chart is shown below. What should the team do next?
Show answerHide answer
Correct answer: DContinue with the sprint work as planned and keep monitoring.
Question 80Choose 1
A new team member joins an agile team. In a previous role, this team member was a
subject matter expert (SME). This team member often directs the team on how to solve
problems based on previous experience.
What should the project manager do first?
Show answerHide answer
Correct answer: DLet the new team member know that even if they know the answer, it is better to give the
team a chance to solve their own problems
That's the last free question in Topic 5: Exam Pool E
You've seen the free 30% (80 of 267 questions). Full access unlocks every question and full-length PMP mock exams (180 questions, 230 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real PMP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.